Status Completed
  1. Submitted Mar 6, 2023
  2. Issued Apr 20, 2023
  3. Expires Sep 17, 2024
  4. Completed Mar 22, 2024

Property

Parcel #
03384-002
Owner
Cady Megan
Acres
1.21
Subdivision
—
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
12023C0383D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
2232
Total Area (Sqft)
3396
Building Height
25
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
23-0255
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - On Hold-Incomplete
  4. Point Review - Printed-Online Application
  5. Plan Review - Documents Required
  6. Plan Review - Documents Required
  7. Plan Review - Documents Required
  8. Plan Review - Building Approved
  9. Plan Review - Electrical Approved
  10. Plan Review - Mechanical Approved
  11. Plan Review - Plumbing Approved
  12. Plan Review - Fuel/Gas Approved
  13. Plan Review - Reviewed
  14. Zoning Review - Reviewed
  15. Plan Review - Documents Required
  16. Final Review - Reviewed
  17. Final Review - Reviewed
  18. Final Review - Payment Needed
  19. Permit Issued
  20. Final Review - Payment Needed

Contractors

  • Mark A Ganskop

    Express Plumbing Inc

    License
    CFC1428040
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Ralph W Laverdure

    Rwl Roofing Llc

    License
    CCC1328590
    Title
    Roofing Contractor
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Everton D Ruddock

    D&s Lighting Inc

    License
    EC13003800
    Title
    Electrical Contractor
    Role
    Subcontractor
  • Rodney L Cribbs

    Quality Air Care Llc

    License
    RA13067616
    Title
    Reg. A/c Class “b”
    Role
    Subcontractor

    County License & State License & Liability Insurance Expired.

  • Charles A Johnson

    Charles Johnson Construction, Inc

    License
    CBC1265794
    Title
    Cert. Building
    Role
    Contractor

    County License & State License Expired.

Inspections

  1. May 1, 2023

    Passed: Engineering - Setbacks

    Inspected by Gary Pitzer

  2. May 1, 2023

    Passed: Building - Footer

    Steel On Supports, Steel Electric Bond In Place

    Inspected by Gary Pitzer

  3. May 22, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Drainage And Turn Ups For Vents Only, Holding Head Water

    Inspected by Gary Pitzer

  4. May 24, 2023

    Electrical -1st Underground Rough–In

    Underslad Conduit Kitchen Area

    Inspected by Gary Pitzer

  5. May 24, 2023

    Passed: Building - Slab

    Wire And Taped Plastic

    Inspected by Gary Pitzer

  6. Jun 16, 2023

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  7. Jun 16, 2023

    Release to power company

    Inspected by Anthony Aslan

  8. Jun 27, 2023

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  9. Aug 3, 2023

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  10. Aug 3, 2023

    Passed: Building - Wall Sheathing

    Windows In And Fastened

    Inspected by Gary Pitzer

  11. Aug 21, 2023

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Gary Pitzer

  12. Aug 21, 2023

    Passed: Building - Framing

    Inspected by Gary Pitzer

  13. Aug 21, 2023

    Passed: Building - Strapping

    Inspected by Gary Pitzer

  14. Aug 21, 2023

    Cancelled: Building - Framing

    Inspected by Melissa Garber

  15. Aug 21, 2023

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Melissa Garber

  16. Aug 21, 2023

    Cancelled: Building - Strapping

    Inspected by Melissa Garber

  17. Aug 21, 2023

    Cancelled: Building - Ext Strapping/Wall Sheathing

    Inspected by Melissa Garber

  18. Aug 21, 2023

    Cancelled: Building - Framing

    Inspected by Melissa Garber

  19. Aug 21, 2023

    Cancelled: Building - Strapping

    Inspected by Melissa Garber

  20. Sep 6, 2023

    Passed: Building - Framing

    Exterior Doors

    Inspected by Gary Pitzer

  21. Sep 6, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  22. Sep 27, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  23. Sep 27, 2023

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Gas Holding V20 Psi

    Inspected by Gary Pitzer

  24. Oct 11, 2023

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  25. Oct 23, 2023

    Rescheduled 10/24/2023:Building - Insulation

    Inspected by Gary Pitzer

  26. Oct 24, 2023

    Passed: Building - Insulation

    Inspected by Gary Pitzer

  27. Feb 5, 2024

    Passed: Electrical - Permanent Power

    Inspected by Gary Pitzer

  28. Feb 5, 2024

    Release to power company

    Inspected by Gary Pitzer

  29. Feb 15, 2024

    Septic Release Inspection

    Inspected by Health Dept

  30. Feb 20, 2024

    Release to power company

    Inspected by Melissa Garber

  31. Mar 21, 2024

    Passed: Building - Final

    Inspected by Gary Pitzer