| Septic Release Inspection |
|
Health Dept |
3/14/2023 |
| Passed: Building - Wall Sheathing |
|
Gary Pitzer |
4/24/2023 |
| Cancelled: Building - Framing |
|
Gary Pitzer |
4/24/2023 |
| Cancelled: Building - Roof Decking |
|
Gary Pitzer |
4/24/2023 |
| Cancelled: Electrical - 1st Underground Rough–In |
|
Gary Pitzer |
4/24/2023 |
| Failed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
4/24/2023 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Gary Pitzer |
4/24/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
4/24/2023 |
| Passed: Building - Framing |
|
Gary Pitzer |
5/3/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
5/3/2023 |
| Passed: Building - Insulation |
|
Gary Pitzer |
6/1/2023 |
| Passed: Building - Final |
|
Gary Pitzer |
7/18/2023 |