2/7/2023
|
City of Lake City Notified of Application within City of Lake City LC_GAS, LC_WATER, LC_SEWER.
|
2/7/2023
|
Point Review - Reviewed
NEEDED
* OWNERS PHONE NUMBER
* UPDATED STATE LICENSE AND LIABILITY FOR THOMAS BULOCK
* SIGNED SUB FORM FOR PLUMBING
* EACH TRADE COST TO BE SINGLED OUT
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* MANUAL J
* ENERGY CALCS
* TRUSS ENGINEERING
|
2/7/2023
|
Point Review - Printed-Online Application
NEEDED
* OWNERS PHONE NUMBER
* UPDATED STATE LICENSE AND LIABILITY FOR THOMAS BULOCK
* SIGNED SUB FORM FOR PLUMBING
* EACH TRADE COST TO BE SINGLED OUT
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* MANUAL J
* ENERGY CALCS
* TRUSS ENGINEERING
|
2/20/2023
|
Plan Review - Corrections Needed
NEEDED
* OWNERS PHONE NUMBER
* UPDATED STATE LICENSE AND LIABILITY FOR THOMAS BULOCK
* SIGNED SUB FORM FOR PLUMBING
* EACH TRADE COST TO BE SINGLED OUT
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* MANUAL J 120 SQFT LESS THAN PLANS
|
2/27/2023
|
Plan Review - Corrections Needed
NEEDED
* OWNERS PHONE NUMBER
LIABILITY FOR THOMAS BULOCK
* SIGNED SUB FORM FOR PLUMBING
* EACH TRADE COST TO BE SINGLED OUT
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* MANUAL J 120 SQFT LESS THAN PLANS
|
3/6/2023
|
Plan Review - Corrections Needed
NEEDED
* OWNERS PHONE NUMBER
LIABILITY FOR THOMAS BULOCK
* HOKANSON CURRENT STATE LICENSE
* EACH TRADE COST TO BE SINGLED OUT
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* MANUAL J 120 SQFT LESS THAN PLANS
|
3/13/2023
|
Plan Review - On Hold-Incomplete
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* MANUAL J 120 SQFT LESS THAN PLANS
|
3/20/2023
|
Plan Review - Building Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/20/2023
|
Plan Review - Electrical Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/20/2023
|
Plan Review - Mechanical Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/20/2023
|
Plan Review - Plumbing Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/20/2023
|
Plan Review - Fuel/Gas Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/20/2023
|
Plan Review - Reviewed
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/21/2023
|
Zoning Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/21/2023
|
Zoning Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN OR CITY SEWER AVAILABILITY
*CITY OF LAKE CITY APPROVAL LETTER
*CITY OF LAKE CITY AVAILABILITY LETTER
|
3/23/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
3/27/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
3/28/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
3/29/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
4/3/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
4/5/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
4/10/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
4/12/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
4/12/2023
|
Zoning Review - Documents Required
NEEDED
*CITY OF LAKE CITY APPROVAL LETTER
|
4/13/2023
|
Final Review - Reviewed
|
4/13/2023
|
Zoning Review - Reviewed
|
4/18/2023
|
Final Review - Reviewed
|
4/18/2023
|
Final Review - Payment Needed
|
4/19/2023
|
Permit Issued
Permit #000047006 created and approved.
|