Permit

New Residential Construction

475 SW BLAYLOCK CT
LAKE CITY, FL 32024

Permit #
000046975
Application #
59283
Status Completed
  1. Submitted Mar 1, 2023
  2. Issued Apr 14, 2023
  3. Expires Feb 22, 2025
  4. Completed Aug 26, 2024

Property

Parcel #
03401-008
Owner
Vidal Michael, Vidal Tammy L
Acres
5.00
Subdivision
Rivers Manor Unit 2 Unr
Zoning
A-3
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
12 INCHES ABOVE GRADE NA
Fema map number
12023C0383D
In floodway
N
This is the construction of a
Accessory Dwelling
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setbacks Rear
25'
Stories
1
Heated Area (Sqft)
784
Total Area (Sqft)
784
Building Height
12
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
residential
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
23-0299
If Other, explain the use of the structure.
Mother -In- Law Suite Power Must Come Off Main Source
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
Other (explain)
Sealed roof decking explanation for other option.
metal rib roof - no underlayment

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Plan Review - Plumbing Approved
  3. Plan Review - Mechanical Approved
  4. Plan Review - Electrical Approved
  5. Plan Review - Building Approved
  6. Plan Review - Reviewed
  7. Zoning Review - Processing
  8. Zoning Review - Reviewed
  9. Final Review - Reviewed
  10. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Apr 24, 2023

    Septic Release Inspection

    Inspected by Health Dept

  2. Jun 12, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Need A Collection Box For Documents

    Inspected by Matt Forsyth

  3. Jun 14, 2023

    Passed: Building - Monolithic Slab

    12 Wide 20 Inches Deep

    Inspected by Troy Crews

  4. Jun 14, 2023

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Jun 14, 2023

    Cancelled: Building - Footer

    Inspected by Troy Crews

  6. Jun 14, 2023

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  7. Oct 13, 2023

    Failed: Electrical - 2nd Rough-In

    1. Need All Outlet Boxes To Be Made Ready For Devices, 2. All Metal Boxes To Have Grounding Screw, 3. Boxes Or Ceiling Lights To Be Installed, 4. Feeder Cable To Installed In Electrical Panel

    Inspected by Gary Pitzer

  8. Oct 13, 2023

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  9. Oct 13, 2023

    Failed: Plumbing/Gas - Tub Set/Shower Pan

    Shower Pan Not Set

    Inspected by Gary Pitzer

  10. Oct 13, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  11. Oct 13, 2023

    Failed: Building - Framing

    1. Need Approved Fasteners For All Hangers, 2. Rim Joist To Be Fastened Properly

    Inspected by Gary Pitzer

  12. Oct 25, 2023

    Passed: Building - Framing

    Inspected by Gary Pitzer

  13. Oct 25, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  14. Oct 25, 2023

    Passed: Plumbing/Gas - Tub Set/Shower Pan

    Inspected by Gary Pitzer

  15. Nov 14, 2023

    Passed: Building - Insulation

    Walls And Ceiling Batted

    Inspected by Gary Pitzer

  16. May 10, 2024

    Passed: Engineering - Spot Check

    In Progress With Finish

    Inspected by Gary Pitzer

  17. Aug 26, 2024

    Passed: Building - Final

    Inspected by Gary Pitzer