Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 475 SW BLAYLOCK CT
LAKE CITY, FL 32024
Parcel #: 03401-008
Acres: 5.00
Owner: Vidal Michael, Vidal Tammy L
Subdivision: Rivers Manor Unit 2 Unr
Zoning: A-3
Flood Zone: X
District: 5
Application #: 59283
Permit #: 000046975
Related Permit:
Submitted: Wednesday, March 1, 2023
Issued: Friday, April 14, 2023
Expires: Monday, August 26, 2024
Completed: Monday, August 26, 2024
Status: Completed
Septic Release? Yes
Notes:
POWER TO COME FROM MAIN DWELLING FLOOR ELEVATION 12 INCHES ABOVE EXISTING GRADE PER ENGINEER
Job Details
Finished floor requirement
Fema map number 12023C0485C
This is the construction of a SFD/UTILITY
Setbacks Front 30.00
Setback Side 1 25.00
Setback Side 2 25.00
Setbacks Rear 25.00
Stories 1
Heated Area (Sqft) 900.00
Total Area (Sqft) 1265.00
Building Code Edition Florida Building Code 2017 6th Edition & 2014 National Electrical Code
Septic# (00-0000) or (X00-000) 19-0545
Review Notes
3/9/2023 Point Review - Received-Hard Copy Application MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU. NEEDED: EH APPROVED PAPERWORK - 386.758.1058 RESIDENITAL CHECKLIST MANUAL J ENERGY CALCS SUB -VF FORM
4/5/2023 Plan Review - Plumbing Approved MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU.
4/5/2023 Plan Review - Mechanical Approved MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU.
4/5/2023 Plan Review - Electrical Approved MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU.
4/5/2023 Plan Review - Building Approved MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU.
4/5/2023 Plan Review - Reviewed MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU.
4/5/2023 Zoning Review - Processing MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU.
4/5/2023 Zoning Review - Reviewed MICHAEL: TROY MAY REQUIRE ADDITIONAL DOCUMENTS, IF SO, HE WILL EMAIL YOU. **THERE IS A SIGNIFICANT DIFFERENCE IN THE ELEVATION AT THE ROAD AND THE ELEVATION AT THE PROPOSED HOME SITE. IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED. SPOKE WITH APPLICANT ON 4/5/23 - LW
4/10/2023 Final Review - Reviewed
4/14/2023 Permit Issued Permit #000046975 created and approved.
Contractors
Name/ Business License Title Role
Inspections
Inspection Notes Performed By Date
Septic Release Inspection Health Dept 4/24/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Need A Collection Box For Documents Matt Forsyth 6/12/2023
Passed: Building - Monolithic Slab 12 Wide 20 Inches Deep Troy Crews 6/14/2023
Passed: Engineering - Setbacks Troy Crews 6/14/2023
Cancelled: Building - Footer Troy Crews 6/14/2023
Cancelled: Engineering - Setbacks Troy Crews 6/14/2023
Failed: Electrical - 2nd Rough-In 1. Need All Outlet Boxes To Be Made Ready For Devices, 2. All Metal Boxes To Have Grounding Screw, 3. Boxes Or Ceiling Lights To Be Installed, 4. Feeder Cable To Installed In Electrical Panel Gary Pitzer 10/13/2023
Passed: Mechanical - Rough In Gary Pitzer 10/13/2023
Failed: Plumbing/Gas - Tub Set/Shower Pan Shower Pan Not Set Gary Pitzer 10/13/2023
Passed: Plumbing/Gas - 2nd Rough-In Gary Pitzer 10/13/2023
Failed: Building - Framing 1. Need Approved Fasteners For All Hangers, 2. Rim Joist To Be Fastened Properly Gary Pitzer 10/13/2023
Passed: Building - Framing Gary Pitzer 10/25/2023
Passed: Electrical - 2nd Rough-In Gary Pitzer 10/25/2023
Passed: Plumbing/Gas - Tub Set/Shower Pan Gary Pitzer 10/25/2023
Passed: Building - Insulation Walls And Ceiling Batted Gary Pitzer 11/14/2023
Passed: Engineering - Spot Check In Progress With Finish Gary Pitzer 5/10/2024
Passed: Building - Final Gary Pitzer 8/26/2024