Permit Details

Permit Search

Permit

Storage Building

2916 SW ICHETUCKNEE AVE
LAKE CITY, FL 32024

Permit #
000046687
Application #
59196
Status Completed
  1. Submitted Feb 21, 2023
  2. Issued Mar 8, 2023
  3. Expires Dec 13, 2023
  4. Completed Jun 16, 2023

Property

Parcel #
00472-001
Owner
Jacob Phillip, Jacob Carolyn L
Acres
10.00
Subdivision
Ford Lane Highlands Unr
Zoning
ESA-2
Flood zone
X
District
2

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Accessory Use
Finished floor requirement
Non-Habitable Structure
Fema map number
12023C0370C
In floodway
N
Type of Structure
Garage
Commercial or Residential?
Residential
Total Area (Sqft)
1200
Septic# (00-0000) or (X00-000)
x23-032
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setback Rear
10' accessory
Building Code Construction Type
III
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
storage
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Building Height
12'
Building Length
30'
Building Width
40'
Slab
New
Mechanical
No
Electrical
No
Plumbing
No

Status & Review History

  1. Point Review - Printed-Online Application
  2. Plan Review - Reviewed
  3. Zoning Review - Documents Required
  4. Zoning Review - Documents Required
  5. Zoning Review - Documents Required
  6. Zoning Review - Documents Required
  7. Zoning Review - Reviewed
  8. Final Review - Reviewed
  9. Final Review - Reviewed
  10. Final Review - Payment Needed
  11. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Feb 28, 2023

    Septic Release Inspection

    Inspected by Health Dept

  2. Mar 20, 2023

    Cancelled: Engineering - Setbacks

    Inspected by Melissa Garber

  3. Mar 20, 2023

    Failed: Building - Footer

    Will Need Compaction Test And Footer Work Completed

    Inspected by Matt Forsyth

  4. Apr 6, 2023

    Passed: Building - Footer

    Footing Depth Met Compaction

    Inspected by Matt Forsyth

  5. Apr 6, 2023

    Passed: Engineering - Setbacks

    Inspected by Matt Forsyth

  6. Jun 14, 2023

    Rescheduled 6/16/2023:Building - Final

    Inspected by Matt Forsyth

  7. Jun 16, 2023

    Passed: Building - Final

    Inspected by Matt Forsyth