Permit Details

Permit Search

Permit

New Residential Construction

423 NW COUNTRY LAKE DR
LAKE CITY, FL 32055

Permit #
000046662
Application #
58713
Status Completed
  1. Submitted Jan 24, 2023
  2. Issued Mar 7, 2023
  3. Expires May 15, 2024
  4. Completed Nov 17, 2023

Property

Parcel #
02267-601
Owner
Bryan Zecher Homes, Inc,
Acres
1.10
Subdivision
Country Lake In Woodborough Phase 6
Zoning
RSF-2
Flood zone
X
District
3

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Engineers Elevation Letter
Finished floor requirement
1 FOOT ABOVE ADJACENT GRADE'
Requirement needed
By Nailing Inspection
Document needed is
NA
Document receieved
Yes
Fema map number
12023C0280D
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
2450
Total Area (Sqft)
3546
Building Height
22
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
22-1022
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - Processing
  4. Point Review - Printed-Online Application
  5. Plan Review - Building Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Mechanical Approved
  8. Plan Review - Plumbing Approved
  9. Plan Review - Fuel/Gas Approved
  10. Plan Review - Reviewed
  11. Zoning Review - Reviewed
  12. Final Review - Reviewed
  13. Permit Issued

Contractors

  • Bryan Zecher

    Bryan Zecher Homes Inc

    License
    CBC1257343
    Title
    Building Contractor
    Role
    Contractor
  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Anthony R Franks

    Lane Heating & Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

  • Robert Ogles

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Mar 22, 2023

    Passed: Building - Footer

    Inspected by Anthony Aslan

  2. Mar 22, 2023

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  3. Mar 24, 2023

    Passed: Electrical - Temporary Service

    Temp Electric Only

    Inspected by Gary Pitzer

  4. Mar 24, 2023

    Release to power company

    Inspected by Gary Pitzer

  5. Apr 17, 2023

    Passed: Building - Slab

    Drains, And Chase Piping. Also 2 Underslab Electric Conduits. No Water Or Gas

    Inspected by Gary Pitzer

  6. Apr 26, 2023

    Plumbing/Gas-1st Underground Rough–In

    Done On 4-17-23 Was Marked Wrong As Slab

    Inspected by Gary Pitzer

  7. Apr 26, 2023

    Passed: Building - Slab

    Rebar And Wire, Plastic And Taped

    Inspected by Gary Pitzer

  8. Jun 7, 2023

    Passed: Building - Wall Sheathing

    Inspected by Gary Pitzer

  9. Jun 7, 2023

    Passed: Building - Roof Decking

    Inspected by Gary Pitzer

  10. Jun 9, 2023

    Passed: Building - Framing

    Inspected by Gary Pitzer

  11. Jun 9, 2023

    Passed: Building - Strapping

    Inspected by Gary Pitzer

  12. Jun 30, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Gary Pitzer

  13. Jun 30, 2023

    Passed: Mechanical - Rough In

    Inspected by Gary Pitzer

  14. Jun 30, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Gary Pitzer

  15. Jul 6, 2023

    Passed: Building - Insulation

    Walls Only,battes

    Inspected by Gary Pitzer

  16. Sep 15, 2023

    Release to power company

    Inspected by Melissa Garber

  17. Sep 15, 2023

    Passed: Electrical - Permanent Power

    Drive Inspect In Complete

    Inspected by Gary Pitzer

  18. Sep 15, 2023

    Septic Release Inspection

    Inspected by Health Dept

  19. Nov 17, 2023

    Passed: Building - Final

    Inspected by Gary Pitzer

Documents