| Passed: Building - Footer |
|
Anthony Aslan |
3/22/2023 |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
3/22/2023 |
| Passed: Electrical - Temporary Service |
Temp Electric Only |
Gary Pitzer |
3/24/2023 |
| Release to power company |
|
Gary Pitzer |
3/24/2023 |
| Passed: Building - Slab |
Drains, And Chase Piping. Also 2 Underslab Electric Conduits. No Water Or Gas |
Gary Pitzer |
4/17/2023 |
| Plumbing/Gas-1st Underground Rough–In |
Done On 4-17-23 Was Marked Wrong As Slab |
Gary Pitzer |
4/26/2023 |
| Passed: Building - Slab |
Rebar And Wire, Plastic And Taped |
Gary Pitzer |
4/26/2023 |
| Passed: Building - Wall Sheathing |
|
Gary Pitzer |
6/7/2023 |
| Passed: Building - Roof Decking |
|
Gary Pitzer |
6/7/2023 |
| Passed: Building - Framing |
|
Gary Pitzer |
6/9/2023 |
| Passed: Building - Strapping |
|
Gary Pitzer |
6/9/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
6/30/2023 |
| Passed: Mechanical - Rough In |
|
Gary Pitzer |
6/30/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
6/30/2023 |
| Passed: Building - Insulation |
Walls Only,battes |
Gary Pitzer |
7/6/2023 |
| Release to power company |
|
Melissa Garber |
9/15/2023 |
| Passed: Electrical - Permanent Power |
Drive Inspect In Complete |
Gary Pitzer |
9/15/2023 |
| Septic Release Inspection |
|
Health Dept |
9/15/2023 |
| Passed: Building - Final |
|
Gary Pitzer |
11/17/2023 |