Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 125 SW HERMITAGE GLN
HIGH SPRINGS, FL 32643
Parcel #: 10039-107
Acres: 5.00
Owner: Geiger Farms, Llc,
Subdivision: Hermitage
Zoning: A-3
Flood Zone: X
District: 4
Application #: 58749
Permit #: 000046636
Related Permit:
Submitted: Wednesday, January 18, 2023
Issued: Thursday, March 2, 2023
Expires: Tuesday, February 20, 2024
Completed: Tuesday, February 20, 2024
Status: Completed
Septic Release? Yes
Notes:
FINISHED FLOOR ONE FOOT ABOVE ROAD OR ENGINEER LETTER WITH SURVEYOR CONFIRMATION
Job Details
Elevation regulation Engineers Elevation Letter
Finished floor requirement 56.12'
Requirement needed By Nailing Inspection
Document needed is a Surveyor letter giving the Finished Floor Elevation
Document receieved Yes
Fema map number 12023C0551C
In floodway N
This is the construction of a Single Family Dwelling
Setbacks Front 30'
Setback Side 1 25'
Setback Side 2 30' (2nd front)
Setbacks Rear 25'
Stories 2
Heated Area (Sqft) 3116
Total Area (Sqft) 5020
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000) 23-0002
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Review Notes
1/18/2023 Point Review - Received-Hard Copy Application
1/18/2023 Point Review - Reviewed
1/26/2023 Plan Review - Corrections Needed
1/30/2023 Plan Review - On Hold-Incomplete
2/6/2023 Plan Review - Processing
2/13/2023 Plan Review - Documents Required
2/14/2023 Plan Review - Building Approved
2/14/2023 Plan Review - Electrical Approved
2/14/2023 Plan Review - Mechanical Approved
2/14/2023 Plan Review - Plumbing Approved
2/14/2023 Plan Review - Fuel/Gas Approved
2/14/2023 Plan Review - Reviewed
2/20/2023 Zoning Review - Corrections Needed
2/21/2023 Zoning Review - Corrections Needed
2/21/2023 Zoning Review - Reviewed
2/23/2023 Final Review - Documents Required
2/28/2023 Final Review - Reviewed
2/28/2023 Final Review - Payment Needed
3/2/2023 Permit Issued
Contractors
Name/ Business License Title Role
Jerry A Lerner
Lerner Luxury Properties Llc
CBC015604 Building Contractor Contractor
Ryan C Beville
Rbi Electrical Contracting Llc
EC13004236 Electrical Contractor Subcontractor
Matthew J Mcclellan
Hometown Heating And Air Inc
County License & State License & Liability Insurance & Workers Comp Expired.
CAC1818078 Class B Air Conditioning Subcontractor
Paul K Coleman
Colemans Plumbing Inc.
CFC1425624 Certified Plumbing Subcontractor
Benjamin T Keeler
Keeler Roofing, Llc
CCC1330509 Cert. Roofing Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Electrical - Temporary Service Anthony Aslan 3/3/2023
Release to power company Anthony Aslan 3/3/2023
Passed: Engineering - Setbacks Anthony Aslan 3/3/2023
Passed: Building - Footer Per Florida Statue Noc To Be Posted On Site And Permit Anthony Aslan 3/3/2023
Rescheduled 3/14/2023:Plumbing/Gas - 1st Underground Rough–In Emaleigh Williams 3/13/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Need Engineer Letter Or Confirmation Of One Foot Above Road Prior To Slab Pour. Troy Crews 3/14/2023
Passed: Building - Slab Anthony Aslan 3/16/2023
Passed: Building - Roof Decking Anthony Aslan 4/26/2023
Passed: Building - Ext Strapping/Wall Sheathing Anthony Aslan 4/26/2023
Passed: Building - Wall Sheathing Anthony Aslan 4/26/2023
Cancelled: Building - Rated Assembly Fastening Anthony Aslan 6/7/2023
Passed: Building - Framing Missing Nails Bay Window Anthony Aslan 6/7/2023
Passed: Building - Strapping Anthony Aslan 6/7/2023
Passed: Electrical - 2nd Rough-In Anthony Aslan 6/7/2023
Passed: Plumbing/Gas - 2nd Rough-In Anthony Aslan 6/7/2023
Failed: Mechanical - Rough In Missing Gaskets Returns And Supplies, Can Stock On Returns Outside Of Duct Board, Exhaust Fans Connections To Roof, Kitchen Exhaust Duct No Tape On Pipe Joints. Anthony Aslan 6/7/2023
Passed: Mechanical - Rough In Anthony Aslan 6/13/2023
Passed: Building - Insulation Anthony Aslan 6/13/2023
Passed: Electrical - Permanent Power Need Septic Release Anthony Aslan 8/16/2023
Release to power company Anthony Aslan 9/6/2023
Septic Release Inspection Health Dept 9/6/2023
Failed: Building - Final -both Upstairs Bathrooms Gfci's Open Ground, Open Neutral -outlet Cover Missing In Laundry Room -both A/c Refrigerant Lines Need Uv Protective Insulation -missing Back Flow On Hose Bib By Electrical Panel gas Not Connected To Water Heater Or Outside Grill Anthony Aslan 2/9/2024
Passed: Building - Final Corrections Made Anthony Aslan 2/20/2024