Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Initial Driveway |
|
Smith, Blake |
3/9/2023 |
Rescheduled 3/13/2023:Building - Footer |
|
Gary Pitzer |
3/13/2023 |
Rescheduled 3/13/2023:Engineering - Setbacks |
|
Gary Pitzer |
3/13/2023 |
Passed: Engineering - Setbacks |
|
Gary Pitzer |
3/13/2023 |
Passed: Building - Footer |
|
Gary Pitzer |
3/13/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
No Gas Or Electric , Under Slab Plumbing Only |
Gary Pitzer |
3/27/2023 |
Passed: Building - Slab |
|
Troy Crews |
3/28/2023 |
Passed: Electrical - Temporary Service |
|
Gary Pitzer |
4/4/2023 |
Release to power company |
|
Gary Pitzer |
4/4/2023 |
Passed: Building - Wall Sheathing |
|
Gary Pitzer |
4/25/2023 |
Passed: Building - Roof Decking |
Partial Section Of Roof, South End Section Of Main Portion Of House, North Secfoon To Follow |
Gary Pitzer |
5/4/2023 |
Passed: Building - Roof Decking |
|
Gary Pitzer |
5/25/2023 |
Passed: Electrical - 2nd Rough-In |
|
Gary Pitzer |
8/4/2023 |
Passed: Mechanical - Rough In |
|
Gary Pitzer |
8/4/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Gary Pitzer |
8/4/2023 |
Failed: Building - Framing |
Steps Not To Code, First Step 7"1/2 , 2nd Step 8". Also Need Support Under Landing |
Gary Pitzer |
8/4/2023 |
Building-Framing |
Stairs To Be Ok By Final With Floor Finish And Stair Tread Finish |
Gary Pitzer |
8/15/2023 |
Passed: Building - Insulation |
Foam And Batts |
Gary Pitzer |
9/29/2023 |
Septic Release Inspection |
|
Health Dept |
12/4/2023 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
2/21/2024 |
Passed: Electrical - Permanent Power |
|
Gary Pitzer |
3/6/2024 |
Release to power company |
|
Gary Pitzer |
3/6/2024 |
Rescheduled 5/2/2024:Building - Final |
|
Troy Crews |
5/1/2024 |
Passed: Engineering - Final Driveway |
|
Smith, Blake |
5/2/2024 |
Cancelled - Duplicate Inspection Requested: Engineering - Final Driveway |
|
Smith, Blake |
5/2/2024 |
Passed: Building - Final |
|
Gary Pitzer |
5/2/2024 |