2/8/2023
|
Application pending.
|
2/8/2023
|
Application submitted by applicant.
|
2/10/2023
|
Point Review - Reviewed
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* LIABILITY FOR STUART AMIRA
* UPDATED STATE LICENSE, WORKERS COMP, LIABILITY FOR DAVID PABST
|
2/10/2023
|
Point Review - Printed-Online Application
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
* LIABILITY FOR STUART AMIRA
* UPDATED STATE LICENSE, WORKERS COMP, LIABILITY FOR DAVID PABST
|
2/21/2023
|
Plan Review - Building Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
2/21/2023
|
Plan Review - Electrical Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
2/21/2023
|
Plan Review - Mechanical Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
2/21/2023
|
Plan Review - Plumbing Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
2/21/2023
|
Plan Review - Fuel/Gas Approved
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
2/21/2023
|
Plan Review - Reviewed
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
|
2/22/2023
|
Zoning Review - Reviewed
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*THERE IS A 4' DIFFERENCE IN THE ELEVATION AT THE PROPOSED HOME SITE AND THE MINIMUM FLOOR ELEVATION OF 98' (1' ABOVE THE ROAD). IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
2/23/2023
|
Final Review - Documents Required
NEEDED
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*THERE IS A 4' DIFFERENCE IN THE ELEVATION AT THE PROPOSED HOME SITE AND THE MINIMUM FLOOR ELEVATION OF 98' (1' ABOVE THE ROAD). IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
2/24/2023
|
Final Review - Documents Required
NEEDED
*OWNERS PHONE NUMBER
* ENVIRONMENTAL HEALTH SIGNED SITE PLAN
*THERE IS A 4' DIFFERENCE IN THE ELEVATION AT THE PROPOSED HOME SITE AND THE MINIMUM FLOOR ELEVATION OF 98' (1' ABOVE THE ROAD). IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
3/1/2023
|
Final Review - Reviewed
*THERE IS A 4' DIFFERENCE IN THE ELEVATION AT THE PROPOSED HOME SITE AND THE MINIMUM FLOOR ELEVATION OF 98' (1' ABOVE THE ROAD). IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
3/1/2023
|
Final Review - Payment Needed
*THERE IS A 4' DIFFERENCE IN THE ELEVATION AT THE PROPOSED HOME SITE AND THE MINIMUM FLOOR ELEVATION OF 98' (1' ABOVE THE ROAD). IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
3/2/2023
|
Permit Issued
Permit #000046628 created and approved.
|
7/19/2023
|
Final Review - Payment Needed
*THERE IS A 4' DIFFERENCE IN THE ELEVATION AT THE PROPOSED HOME SITE AND THE MINIMUM FLOOR ELEVATION OF 98' (1' ABOVE THE ROAD). IF THE MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|