2/10/2023
|
Application pending.
|
2/10/2023
|
Application submitted by applicant.
|
2/10/2023
|
City of Lake City
City of Lake City Notified of Application within City of Lake City LC_GAS, LC_WATER, LC_SEWER.
|
2/13/2023
|
Final Review - Corrections Needed
NEEDED:
*LANDOWNER AFFIDAVIT FROM TANYA JOHNSON TO ADRIAN BOATRIGHT
*CONTRACTOR AUTHORIZATION FOR MABEL QUINTERO
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/23/2023
|
Final Review - Corrections Needed
NEEDED:
*LANDOWNER AFFIDAVIT FROM TANYA JOHNSON TO ADRIAN BOATRIGHT
*CONTRACTOR AUTHORIZATION FOR MABEL QUINTERO-- HAND SIGNED OR ESIGNED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/27/2023
|
Point Review - Reviewed
NEEDED:
*CONTRACTOR AUTHORIZATION FOR MABEL QUINTERO-- HAND SIGNED OR ESIGNED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/27/2023
|
Plan Review - Building Approved
NEEDED:
*CONTRACTOR AUTHORIZATION FOR MABEL QUINTERO-- HAND SIGNED OR ESIGNED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/27/2023
|
Plan Review - Reviewed
NEEDED:
*CONTRACTOR AUTHORIZATION FOR MABEL QUINTERO-- HAND SIGNED OR ESIGNED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/27/2023
|
Zoning Review - Reviewed
NEEDED:
*CONTRACTOR AUTHORIZATION FOR MABEL QUINTERO-- HAND SIGNED OR ESIGNED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/27/2023
|
Final Review - Corrections Needed
NEEDED:
*CONTRACTOR AUTHORIZATION FOR MABEL QUINTERO-- HAND SIGNED OR ESIGNED
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/27/2023
|
Final Review - Reviewed
NEEDED:
***PRIOR TO INSPECTIONS***
RECORDED NOC
|
2/27/2023
|
Final Review - Payment Needed
|
2/27/2023
|
Permit Issued
Permit #000046593 created and approved.
|