12/6/2022
|
Application pending.
|
12/6/2022
|
Application submitted by applicant.
|
12/7/2022
|
Point Review - On Hold-Incomplete
BRITTANY: INCOMPLETE - PLEASE UPLOAD ALL NECESSARY DOCS.
911
PLANS
ENERGY CALCS
MANUAL J
SUB-VF FORM - MISSING - ALSO, PLEASE ADD NAMES OF SUBS IN REQUESTED SUB-CONTRACTORS FIELD
CONTRACTOR LETTER OF AUTHORIZATION
|
12/7/2022
|
Application Converted
Application was converted from Storage Building to New Residential Construction
|
12/7/2022
|
Point Review - Printed-Online Application
BRITTANY:
NEEDED:
APPROVED EH PAPERWORK
PRODUCT APPROVAL SHEET
VAN MERSBREGEN - CERTIFICATE OF LIABILITY & WORKER'S COMP
CONTRACTOR LETTER OF AUTHORIZATION
|
12/20/2022
|
Plan Review - Building Approved
BRITTANY:
NEEDED:
APPROVED EH PAPERWORK
CONTRACTOR LETTER OF AUTHORIZATION
|
12/20/2022
|
Plan Review - Electrical Approved
BRITTANY:
NEEDED:
APPROVED EH PAPERWORK
CONTRACTOR LETTER OF AUTHORIZATION
|
12/20/2022
|
Plan Review - Mechanical Approved
BRITTANY:
NEEDED:
APPROVED EH PAPERWORK
CONTRACTOR LETTER OF AUTHORIZATION
|
12/20/2022
|
Plan Review - Plumbing Approved
BRITTANY:
NEEDED:
APPROVED EH PAPERWORK
CONTRACTOR LETTER OF AUTHORIZATION
|
12/20/2022
|
Plan Review - Reviewed
BRITTANY:
NEEDED:
APPROVED EH PAPERWORK
CONTRACTOR LETTER OF AUTHORIZATION
|
12/21/2022
|
Zoning Review - Corrections Needed
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
APPROVED EH PAPERWORK
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
NEW SITE PLAN SHOWING A MINIMUM OF 25' SIDE SETBACK
ENGINEERED FLOOD VENTS
|
12/29/2022
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
NEW SITE PLAN SHOWING A MINIMUM OF 25' SIDE SETBACK
ENGINEERED FLOOD VENTS
|
1/3/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
NEW SITE PLAN SHOWING A MINIMUM OF 25' SIDE SETBACK
ENGINEERED FLOOD VENTS
|
1/5/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
NEW SITE PLAN SHOWING A MINIMUM OF 25' SIDE SETBACK
ENGINEERED FLOOD VENTS
|
1/9/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
ENGINEERED FLOOD VENTS
|
1/17/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
ENGINEERED FLOOD VENTS
|
1/20/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
|
1/23/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
|
1/27/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
CONTRACTOR LETTER OF AUTHORIZATION
1' RISE
ELEVATION CERTIFICATE
|
2/1/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
1' RISE LETTER
ELEVATION CERTIFICATE NEEDED FOR C.O.
|
2/6/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
1' RISE LETTER
ELEVATION CERTIFICATE NEEDED FOR C.O.
|
2/8/2023
|
Zoning Review - Documents Required
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
NEEDED:
1' RISE LETTER
ELEVATION CERTIFICATE NEEDED FOR C.O.
|
2/10/2023
|
Zoning Review - Reviewed
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
* A STOVE IS ALLOWED SINCE WE ARE PERMITTING THIS AS AN ACCESSORY DWELLING UNIT.
NEEDED:
ELEVATION CERTIFICATE NEEDED FOR C.O.
|
2/13/2023
|
Final Review - Reviewed
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
* A STOVE IS ALLOWED SINCE WE ARE PERMITTING THIS AS AN ACCESSORY DWELLING UNIT.
NEEDED:
ELEVATION CERTIFICATE NEEDED FOR C.O.
|
2/13/2023
|
Final Review - Reviewed
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
* A STOVE IS ALLOWED SINCE WE ARE PERMITTING THIS AS AN ACCESSORY DWELLING UNIT.
NEEDED:
ELEVATION CERTIFICATE NEEDED FOR C.O.
|
2/23/2023
|
Permit Issued
Permit #000046577 created and approved.
|
10/30/2023
|
Final Review - Reviewed
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
* A STOVE IS ALLOWED SINCE WE ARE PERMITTING THIS AS AN ACCESSORY DWELLING UNIT.
NEEDED:
ELEVATION CERTIFICATE NEEDED FOR C.O.
|
10/30/2023
|
Final Review - Payment Needed
BRITTANY: POWER MUST COME FROM THE PRIMARY DWELLING - CANNOT BE METERED SEPERATELY
* A STOVE IS ALLOWED SINCE WE ARE PERMITTING THIS AS AN ACCESSORY DWELLING UNIT.
NEEDED:
ELEVATION CERTIFICATE NEEDED FOR C.O.
|