6/1/2022
|
City of Lake City Notified of Application within City of Lake City LC_GAS, LC_WATER, LC_SEWER.
|
6/1/2022
|
Point Review - Received-Hard Copy Application
NEEDED:
*ENGINEERING FOR RAFTERS
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
6/1/2022
|
Point Review - Reviewed
NEEDED:
*ENGINEERING FOR RAFTERS
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
6/9/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
6/13/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
6/17/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
6/23/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
6/27/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
7/5/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
7/11/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
7/12/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
7/19/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
8/1/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
8/3/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
8/8/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
8/15/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
8/17/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
9/7/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
9/13/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
*CITY OF LAKE CITY APPROVAL LETTER- PENDING
|
9/30/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
|
12/14/2022
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
|
1/3/2023
|
Plan Review - Documents Required
NEEDED:
*ENGINEERING FOR ROOF SYSTEM SEALED
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
|
1/4/2023
|
Zoning Review - Reviewed
NEEDED:
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
|
1/4/2023
|
Final Review - Documents Required
NEEDED:
*SIGNED ROOFING SUB VF
*UPDATED LIABILITY FOR SANCHEZ
|
1/6/2023
|
Final Review - Documents Required
NEEDED:
*SIGNED ROOFING SUB VF
|
1/17/2023
|
Final Review - Payment Needed
|
2/22/2023
|
Permit Issued
Permit #000046569 created and approved.
|