Permit Details

Permit Search

Permit

Communications Tower

917 SW CHARLES TER
LAKE CITY, FL 32024

Permit #
000046554
Application #
58986
Status Completed
  1. Submitted Feb 7, 2023
  2. Issued Sep 19, 2023
  3. Expires Dec 23, 2024
  4. Completed Jun 26, 2024

Property

Parcel #
03249-000
Owner
American Tower Corporation (tower Lessee)
Acres
123.37
Subdivision
—
Zoning
A-3
Flood zone
X
District
2

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0360C
This is the construction of a:
THE PROPOSED PROJECT INCLUDES INSTALLING EQUIPMENT CABINETS ON A PROPOSED CONCRETE PAD INSIDE A 10' X15' GROUND SPACE WITHIN THE EXISTING COMPOUND, AND INSTALLING NEW EQUIPMENT AND MOUNTS ON THE EXISTING TOWER.
Select access to property:
Existing Drive
Total Estimated Cost
20000
Tower Height
266.17
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Is this a new or existing tower?
Existing
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. Point Review - On Hold-Incomplete
  4. Point Review - Printed-Online Application
  5. Plan Review - Building Approved
  6. Plan Review - Reviewed
  7. Zoning Review - Reviewed
  8. Final Review - Reviewed
  9. Final Review - Reviewed
  10. Final Review - Payment Needed
  11. Permit Issued
  12. Final Review - Payment Needed
  13. Permit Renewed
  14. Final Review - Payment Needed
  15. Plan Review - Reviewed

Contractors

  • Larry Sweatt

    Ericsson Inc

    License
    CGC1532010
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • Frank Kisel

    Ericsson Inc

    License
    EC13009490
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Feb 26, 2024

    Passed: Building - Slab

    12 Inch Slab 2 Matts #5

    Inspected by Troy Crews

  2. Mar 4, 2024

    Passed: Electrical - Permanent Power

    New Service Co Location

    Inspected by Troy Crews

  3. Mar 4, 2024

    Release to power company

    Inspected by Troy Crews

  4. Mar 4, 2024

    Passed: Electrical - 1st Underground Rough–In

    All Binding In Place

    Inspected by Troy Crews

  5. Jun 24, 2024

    Rescheduled 6/25/2024:Building - Final

    Inspected by Troy Crews

  6. Jun 24, 2024

    Rescheduled 6/25/2024:Building - Final

    Inspected by Troy Crews

  7. Jun 24, 2024

    Rescheduled 6/26/2024:Building - Final

    Inspected by Troy Crews

  8. Jun 26, 2024

    Passed: Building - Final

    Inspected by Troy Crews