Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Commercial Construction Permit

Address 943 N MARION AVE
LAKE CITY, FL 32055
Parcel #: 11228-000
Acres: 0.48
Owner: Lg Transit Llc,
Subdivision: Catheys Survey
Zoning:
Flood Zone: X
District: 1
Application #: 59055
Permit #: 000046550
Related Permit:
Submitted: Monday, February 13, 2023
Issued: Friday, February 17, 2023
Expires: Monday, June 26, 2023
Completed: Monday, June 26, 2023
Status: Completed
Septic Release? Yes
Notes:

LAKE CITY UTLITY CUSTOMER SERVICE NOTES Water and sewer taps have been completed for this location. LAKE CITY ZONING NOTES Site plan was approved by the Planning and Zoning Board on 01/04/23 LAKE CITY CODE ENFORCEMENT CASE NOTES None
Job Details
Finished floor requirement
Fema map number 12023C0284D
Sign Type Ground
Is the sign illuminated? Yes
If "Yes", explain (LED, Flashing, etc...) led
Is this sign replacing an existing sign? No
Total sign height 8
Ground Clearance 0
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Service Amps 30
Review Notes
2/13/2023 City of Lake City Notified of Application within City of Lake City LC_GAS, LC_WATER, LC_SEWER.
2/13/2023 Application Converted Application was converted from New Residential Construction to New Commercial Construction
2/13/2023 Point Review - Received-Hard Copy Application NEEDED: *ROOF OPTION SELECTED *CITY OF LAKE CITY APPROVAL LETTER *CITY AVAILABILITY LETTER
2/13/2023 Plan Review - Documents Required NEEDED: *ROOF OPTION SELECTED *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION STRUCTURAL PLANS, ENERGY CALCULATIONS, MANUAL J
2/15/2023 Plan Review - Documents Required NEEDED: *ROOF OPTION SELECTED *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION ENERGY CALCULATIONS, MANUAL J
2/15/2023 Plan Review - Plumbing Approved NEEDED: *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION
2/15/2023 Plan Review - Mechanical Approved NEEDED: *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION
2/15/2023 Plan Review - Electrical Approved NEEDED: *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION
2/15/2023 Plan Review - Building Approved NEEDED: *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION
2/15/2023 Zoning Review - Documents Required NEEDED: *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION
2/16/2023 Zoning Review - Documents Required NEEDED: *CITY OF LAKE CITY APPROVAL LETTER *ESTIMATIED COST OF CONSTRUCTION BROKEN DOWN ELECTRIC, PLUMBING, HVAC, BUILDING
2/17/2023 Zoning Review - Reviewed
2/17/2023 Final Review - Reviewed
2/17/2023 Final Review - Reviewed
2/17/2023 Final Review - Payment Needed
2/17/2023 Permit Issued Permit #000046550 created and approved.
Contractors
Name/ Business License Title Role
Anthony George,jr.
George Construction Llc
Workers Comp Expired.
CGC016583 General Contractor Contractor
Charles R Sanford
Energy Electric Inc
EC0000175 Cert. Electrical Subcontractor
Harry D Moseley Sr
Harrys Heating & Air Conditioning Inc
Liability Insurance Expired.
RA0030316 Class A A/c Contractor Subcontractor
Roger Whiddon
Lake City Plumbing Inc
CFC1428686 Cert Plumbing Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Plumbing/Gas - 1st Underground Rough–In Troy Crews 2/24/2023
Cancelled: Building - Monolithic Slab Melissa Garber 2/27/2023
Cancelled: Engineering - Setbacks Melissa Garber 2/27/2023
Passed: Building - Monolithic Slab Troy Crews 2/28/2023
Passed: Engineering - Setbacks Meets Setbacks On City Approval Letter. Troy Crews 2/28/2023
Passed: Building - Ext Strapping/Wall Sheathing Troy Crews 3/13/2023
Passed: Plumbing/Gas - 2nd Rough-In Check Hot Water Lines With Pressure Troy Crews 4/3/2023
Passed: Building - Framing Troy Crews 4/3/2023
Passed: Electrical - 2nd Rough-In Troy Crews 4/17/2023
Passed: Mechanical - Rough In Troy Crews 4/17/2023
Passed: Building - Insulation Troy Crews 4/21/2023
Passed: Electrical - Permanent Power Troy Crews 5/17/2023
Release to power company Troy Crews 5/17/2023
Certificate-Release Certificate Troy Crews 6/26/2023
Passed: Building - Final Owner To Change Bathroom Door Handle To Paddle Type Need Fire Final For Co Troy Crews 6/26/2023
Passed: Fire - Fire Final Dwight Boozer 6/26/2023