Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 235 SE SILKY CT
HIGH SPRINGS, FL 32643
Parcel #: 09860-013
Acres: 2.25
Owner: Stevens Matthew, Stevens Angela Marie
Subdivision: Hawks Ridge Acres
Zoning: A-3
Flood Zone: X
District: 4
Application #: 58755
Permit #: 000046477
Related Permit: Culvert Waiver: 000046478
Submitted: Thursday, January 19, 2023
Issued: Tuesday, February 7, 2023
Expires: Wednesday, May 7, 2025
Completed:
Status: Final Review - Payment Needed
Septic Release? No
Notes:
MFE 1' ABOVE THE ROAD
Job Details
This is the construction of a Single Family Dwelling
Heated Area (Sqft) 750
Total Area (Sqft) 1015
Stories 1
Building Height 12
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Setbacks Front 30'
Setback Side 1 25'
Setback Side 2 25'
Setbacks Rear 25'
Septic# (00-0000) or (X00-000) 22-0869
Service Amps 200
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Elevation regulation Minimum Requirement
Finished floor requirement One foot above the road
Fema map number 12023C0512C
In floodway N
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) Other (explain)
Sealed roof decking explanation for other option. part of the building
Review Notes
1/18/2023 Application pending.
1/19/2023 Application submitted by applicant.
1/24/2023 Point Review - Printed-Online Application NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
1/24/2023 Point Review - Reviewed
1/27/2023 Plan Review - Building Approved NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
1/27/2023 Plan Review - Electrical Approved NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
1/27/2023 Plan Review - Mechanical Approved NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
1/27/2023 Plan Review - Plumbing Approved NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
1/27/2023 Plan Review - Fuel/Gas Approved NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
1/27/2023 Plan Review - Reviewed NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
2/2/2023 Zoning Review - Documents Required NEEDED * IF FULL BUILD OUT SIGNED MEP SUB FORM
2/6/2023 Zoning Review - Reviewed
2/7/2023 Final Review - Reviewed
2/7/2023 Final Review - Reviewed
2/7/2023 Final Review - Payment Needed
2/7/2023 Permit Issued Permit #000046477 created and approved.
3/7/2023 Final Review - Payment Needed
3/9/2023 Final Review - Payment Needed
Contractors

This is an owner builder project.

Name/ Business License Title Role
Inspections
Inspection Notes Performed By Date
Failed: Electrical - Permanent Power No Gfci Outlets Anthony Aslan 3/8/2023
Passed: Electrical - Temporary Service Correction Made Anthony Aslan 3/13/2023
Release to power company Anthony Aslan 3/13/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Anthony Aslan 7/12/2023
Passed: Building - Monolithic Slab No Ground Wire On Footing Steel Anthony Aslan 7/14/2023
Passed: Engineering - Setbacks Anthony Aslan 7/14/2023
Passed: Building - Ext Strapping/Wall Sheathing Building Shell Metal Anthony Aslan 12/19/2023
Passed: Engineering - Spot Check Interior Walls Being Framed Anthony Aslan 6/17/2024
Passed: Building - Framing Anthony Aslan 11/8/2024