12/5/2022
|
Application pending.
|
12/6/2022
|
Application submitted by applicant.
|
12/7/2022
|
Point Review - On Hold-Incomplete
BLAKE: PLEASE UPLOAD THE FOLLOWING: INCOMPLETE
DIGITAL PLANS
ENERGY CALCS
MANUAL J
|
12/14/2022
|
Point Review - Printed-Online Application
NEEDED:
*SEALED STRUCTURAL PLANS
*ENV HEALTH SIGNED SITE PLAN APPROVAL- CONTACT 386-758-1058
|
12/14/2022
|
Point Review - Reviewed
NEEDED:
*SEALED STRUCTURAL PLANS
*ENV HEALTH SIGNED SITE PLAN APPROVAL- CONTACT 386-758-1058
|
12/28/2022
|
Plan Review - Documents Required
NEEDED:
**TRUSS MISSING TRUSS
*SEALED STRUCTURAL PLANS - RAISED SEAL WE NEED ORIGINALS
|
12/29/2022
|
Plan Review - Documents Required
NEEDED:
*SEALED STRUCTURAL PLANS - RAISED SEAL WE NEED ORIGINALS
|
1/3/2023
|
Plan Review - Documents Required
NEEDED:
*SEALED STRUCTURAL PLANS - RAISED SEAL WE NEED ORIGINALS
|
1/9/2023
|
Plan Review - On Hold-Incomplete
NEEDED:
*SEALED STRUCTURAL PLANS - RAISED SEAL WE NEED ORIGINALS
|
1/11/2023
|
Plan Review - Corrections Needed
NEEDED:
*FIRST PAGE IS THE ONLY PAGE THE SEAL IS ON
|
1/18/2023
|
Plan Review - Building Approved
|
1/18/2023
|
Plan Review - Electrical Approved
|
1/18/2023
|
Plan Review - Mechanical Approved
|
1/18/2023
|
Plan Review - Plumbing Approved
|
1/18/2023
|
Plan Review - Fuel/Gas Approved
|
1/18/2023
|
Plan Review - Reviewed
|
1/24/2023
|
Zoning Review - Reviewed
MFE - 1' ABOVE THE ROAD - IF MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
1/24/2023
|
Final Review - Reviewed
MFE - 1' ABOVE THE ROAD - IF MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
1/26/2023
|
Final Review - Reviewed
MFE - 1' ABOVE THE ROAD - IF MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
1/26/2023
|
Final Review - Payment Needed
MFE - 1' ABOVE THE ROAD - IF MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|
1/27/2023
|
Permit Issued
Permit #000046385 created and approved.
|
2/22/2023
|
Permit Reissued
Permit reissued to reflect updated information.
|
5/17/2023
|
Final Review - Payment Needed
MFE - 1' ABOVE THE ROAD - IF MINIMUM FLOOR ELEVATION CANNOT BE MET THEN AN ENGINEER LETTER WILL BE REQUIRED.
|