Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit

Address 2675 SW TUSTENUGGEE AVE
LAKE CITY, FL 32025
Parcel #: 08931-003
Acres: 2.93
Owner: Stockdale Stanley W, Stockdale Kimberly T
Subdivision:
Zoning: A-3
Flood Zone: X
District: 4
Application #: 57048
Permit #: 000046344
Related Permit:
Submitted: Friday, November 4, 2022
Issued: Tuesday, January 24, 2023
Expires: Friday, March 22, 2024
Completed: Friday, March 22, 2024
Status: Completed
Septic Release? No
Notes:
LEGAL LOT - SFLP2135 MFE 1' ABOVE HIGHEST ADJACENT GRADE
Job Details
Elevation regulation Engineers Elevation Letter
Finished floor requirement 1' ABOVE HIGHEST ADJACENT GRADE
Fema map number 12023C0382D
In floodway N
This is the construction of a Single Family Dwelling
Setbacks Front 30'
Setback Side 1 25'
Setback Side 2 25'
Setbacks Rear 25'
Stories 1
Heated Area (Sqft) 1536
Total Area (Sqft) 2304
Building Height 15
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000) 22-0985
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition) a self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 applied over the entire roof.
Service Amps 200
Review Notes
11/4/2022 Application pending.
11/4/2022 Application submitted by applicant.
11/7/2022 Point Review - Printed-Online Application
11/7/2022 Point Review - Reviewed
11/14/2022 Plan Review - Corrections Needed
11/21/2022 Plan Review - Corrections Needed
11/28/2022 Plan Review - Building Approved
11/28/2022 Plan Review - Electrical Approved
11/28/2022 Plan Review - Mechanical Approved
11/28/2022 Plan Review - Plumbing Approved
11/28/2022 Plan Review - Fuel/Gas Approved
11/28/2022 Plan Review - Reviewed
11/30/2022 Zoning Review - Reviewed
12/1/2022 Final Review - Documents Required
12/5/2022 Final Review - Documents Required
12/8/2022 Final Review - Documents Required
12/9/2022 Final Review - Documents Required
12/14/2022 Final Review - Documents Required
12/19/2022 Final Review - Documents Required
12/28/2022 Final Review - Documents Required
1/3/2023 Final Review - Documents Required
1/5/2023 Final Review - Documents Required
1/9/2023 Final Review - Documents Required
1/17/2023 Final Review - Documents Required
1/18/2023 Final Review - Reviewed
1/18/2023 Final Review - Reviewed
1/18/2023 Final Review - Payment Needed
1/24/2023 Permit Issued
3/11/2024 Final Review - Payment Needed
Contractors
Name/ Business License Title Role
Stan Stockdale
Stan Stockdale Contractor Llc
County License & State License & Liability Insurance & Workers Comp Expired.
CRC1331015 Cert. Residential Contractor
Inspections
Inspection Notes Performed By Date
Passed: Building - Footer Per Plan Gary Pitzer 3/1/2023
Passed: Engineering - Setbacks Gary Pitzer 3/1/2023
Failed: Electrical - Temporary Service Needs Grounding System For Service, No Bonding Screw, Need To Keep Wire From Being Damaged At Knock Out Hole Gary Pitzer 3/1/2023
Failed: Electrical - Temporary Service Bonding Screw Not On Site To Be Found Nor In Place, Gary Pitzer 3/3/2023
Passed: Electrical - Temporary Service Gary Pitzer 3/20/2023
Release to power company Gary Pitzer 3/20/2023
Passed: Building - Framing Floor Framing Only Gary Pitzer 6/21/2023
Passed: Building - Ext Strapping/Wall Sheathing Gary Pitzer 8/29/2023
Passed: Building - Roof Decking Gary Pitzer 8/29/2023
Passed: Building - Framing Gary Pitzer 8/29/2023
Passed: Building - Strapping Gary Pitzer 8/29/2023
Passed: Building - Wall Sheathing Gary Pitzer 10/25/2023
Passed: Electrical - 1st Underground Rough–In Gary Pitzer 12/13/2023
Cancelled: Plumbing/Gas - 1st Underground Rough–In Gary Pitzer 12/13/2023
Passed: Plumbing/Gas - 2nd Rough-In Gary Pitzer 12/19/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Gary Pitzer 12/19/2023
Passed: Mechanical - Rough In Gary Pitzer 12/27/2023
Passed: Building - Insulation Batts Gary Pitzer 12/27/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Gas Line And Preasured Gary Pitzer 2/20/2024
Passed: Electrical - Permanent Power Gary Pitzer 3/12/2024
Release to power company Gary Pitzer 3/12/2024
Passed: Building - Final Owner Builder 1 Bedroom, Bathroom, Sink In Kitchen Gary Pitzer 3/21/2024