Inspection |
Notes |
Performed By |
Date |
Passed: Fire - Plan Review |
|
Lance Hill |
11/7/2022 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
2/3/2023 |
Cancelled: Building - Footer |
Duplicate |
Emaleigh Williams |
2/14/2023 |
Cancelled: Engineering - Setbacks |
Duplicate |
Emaleigh Williams |
2/14/2023 |
Passed: Building - Footer |
Pad Foundations West Half, And Elevator Pit Foundation. Email Threshold Inspections To Troy. |
Troy Crews |
2/15/2023 |
Passed: Engineering - Setbacks |
|
Troy Crews |
2/15/2023 |
Cancelled: Building - Footer |
Duplicate |
Emaleigh Williams |
2/24/2023 |
Cancelled: Engineering - Setbacks |
Duplicate
|
Emaleigh Williams |
2/24/2023 |
Passed: Building - Footer |
Elevator Pit Walls |
Troy Crews |
2/24/2023 |
Passed: Engineering - Setbacks |
|
Troy Crews |
2/24/2023 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
2/24/2023 |
Release to power company |
|
Troy Crews |
2/24/2023 |
Passed: Building - Footer |
Remainder Of Foundations And Footer Steel Ground. |
Troy Crews |
3/2/2023 |
Passed: Engineering - Setbacks |
|
Troy Crews |
3/2/2023 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
3/2/2023 |
Release to power company |
|
Troy Crews |
3/2/2023 |
Passed: Building - Footer |
|
Troy Crews |
3/9/2023 |
Passed: Engineering - Setbacks |
|
Troy Crews |
3/9/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
West Half Of Building Sanitary |
Troy Crews |
3/17/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste Lines East Half Of Building |
Troy Crews |
3/24/2023 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
4/4/2023 |
Passed: Building - Framing |
Interior Framing First Three Floors |
Troy Crews |
8/22/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
10/9/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
All Condensate, And Remainder Of Waste Lies 1 Thru 5 |
Troy Crews |
10/13/2023 |
Cancelled: Plumbing/Gas - 1st Underground Rough–In |
Duplicate Request |
Emaleigh Williams |
11/14/2023 |
Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
11/15/2023 |
Passed: Mechanical - Rough In |
5th Floor Exhaust Venting, O/a Duct |
Anthony Aslan |
11/15/2023 |
Failed: Plumbing/Gas - 2nd Rough-In |
Could Not Locate Workers For Plumber |
Troy Crews |
11/21/2023 |
Passed: Plumbing/Gas - Rain Leader |
Partial Roof Drains Topped Off At Roof |
Troy Crews |
11/21/2023 |
Passed: Electrical - 2nd Rough-In |
5 Th Floor Rough In |
Troy Crews |
11/29/2023 |
Passed: Building - Framing |
Framing 5th Floor |
Troy Crews |
11/30/2023 |
Passed: Building - Fire Rated Wall |
First Layer Shaft Walls 5th Floor |
Troy Crews |
12/4/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
12/4/2023 |
Passed: Plumbing/Gas - Sanitary |
|
Troy Crews |
12/4/2023 |
Passed: Plumbing/Gas - Water Pipe |
|
Troy Crews |
12/4/2023 |
Passed: Mechanical - Rough In |
4th Floor Work In Shafts |
Anthony Aslan |
12/6/2023 |
Passed: Electrical - 2nd Rough-In |
Guestrooms Only, Hallway And Equipment Rooms Not Complete |
Troy Crews |
12/8/2023 |
Passed: Mechanical - Rough In |
5th, 4th, Floor Good To Wrap Fresh Air
3rd Floor Exhaust Duct
1st Floor Partial To Wrap Ducts |
Anthony Aslan |
12/19/2023 |
Passed: Building - Fire Rated Wall |
Hallways 4 And 5 |
Troy Crews |
1/4/2024 |
Passed: Mechanical - Rough In |
Third Floor Fresh Air Duct |
Anthony Aslan |
1/10/2024 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
1/11/2024 |
Passed: Building - Insulation |
|
Troy Crews |
1/29/2024 |
Passed: Electrical - 2nd Rough-In |
Working On A Few Soffit Lights. |
Troy Crews |
1/31/2024 |
Passed: Building - Insulation |
|
Troy Crews |
2/1/2024 |
Rescheduled 2/5/2024:Fire - Underground Main - Hydro |
|
Troy Crews |
2/5/2024 |
Rescheduled 2/6/2024:Fire - Underground Main - Hydro |
|
Troy Crews |
2/6/2024 |
Rescheduled 2/7/2024:Fire - Underground Main - Hydro |
|
Troy Crews |
2/7/2024 |
Passed: Building - Insulation |
4 And 5 |
Troy Crews |
2/9/2024 |
Cancelled: Building - Footer |
|
Troy Crews |
2/9/2024 |
Cancelled: Engineering - Setbacks |
|
Troy Crews |
2/9/2024 |
Passed: Mechanical - Rough In |
Insulation, Fire Damper Screws Need Correction |
Anthony Aslan |
2/15/2024 |
Cancelled: Electrical - Permanent Power |
|
Troy Crews |
2/26/2024 |
Passed: Building - Insulation |
2 Nd Floo |
Troy Crews |
2/26/2024 |
Passed: Electrical - Permanent Power |
Main Only Room To Be Locked Out Under Control Of Electrician |
Troy Crews |
2/28/2024 |
Release to power company |
|
Troy Crews |
2/28/2024 |
Passed: Mechanical - Rough In |
2nd Floor Room Ducts |
Anthony Aslan |
3/6/2024 |
Passed: Mechanical - Rough In |
Couple Duct To Tight |
Anthony Aslan |
3/19/2024 |
Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
3/19/2024 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
3/19/2024 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
3/27/2024 |
Passed: Electrical - Permanent Power |
Ct Meter Can |
Troy Crews |
3/28/2024 |
Release to power company |
|
Troy Crews |
3/28/2024 |
Failed: Building - Insulation |
Several Areas On Outside Walls Missing Insulation |
Troy Crews |
4/4/2024 |
Passed: Building - Insulation |
Check A Couple Of Spots Around Electric And Plumbing, One Left Of Front Door, One In Rear Of Building Around Outlet Box Left Of Electric Room |
Troy Crews |
4/5/2024 |
Passed: Mechanical - Rough In |
Need Laundry Insulated
supply Drops Conference Rooms |
Anthony Aslan |
4/15/2024 |
Passed: Mechanical - Rough In |
Mastic Refrigerant Lines
install Straps On Ducts |
Anthony Aslan |
4/24/2024 |
Failed: Electrical - 2nd Rough-In |
Electrical Not Complete On First Floor Air Handlers |
Troy Crews |
4/26/2024 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
5/17/2024 |
Cancelled: Electrical - 2nd Rough-In |
|
Troy Crews |
5/20/2024 |
Passed: Electrical - 2nd Rough-In |
Rooftop |
Troy Crews |
6/11/2024 |
Passed: Electrical - Above Ceiling |
5th Floor Hallway |
Troy Crews |
7/10/2024 |
Passed: Electrical - Above Ceiling |
2nd 3rd And 4th Floor Hallways |
Troy Crews |
7/22/2024 |
Passed: Electrical - Above Ceiling |
|
Troy Crews |
8/1/2024 |
Rescheduled 9/3/2024:Electrical - 2nd Rough-In |
|
Troy Crews |
8/29/2024 |
Passed: Electrical - 2nd Rough-In |
All Guest Rooms 1 Thru 5 |
Troy Crews |
9/3/2024 |
Passed: Electrical - 2nd Rough-In |
Remainder Of Interior First Floor |
Troy Crews |
9/17/2024 |
Cancelled: Electrical - 2nd Rough-In |
|
Troy Crews |
9/24/2024 |
Passed: Plumbing/Gas - 2nd Rough-In |
Plumbing Final |
Troy Crews |
10/22/2024 |
Passed: Mechanical - Rough In |
Final Hvac |
Troy Crews |
10/29/2024 |
Certificate-Release Certificate |
Fire Final Good Per Rhet Tompkins |
Troy Crews |
11/14/2024 |
Passed: Building - Final |
Co Pending Fire Final |
Troy Crews |
11/14/2024 |
Passed: Fire - Fire Final |
|
Cpt. Shane Overstreet |
11/15/2024 |
(Requested) City of Lake City Utilities-Lake City Utilities Tap Inspection |
|
|
|