Search pages and services on the county website.
Choose the colors you prefer.
Permit
178 NW COMMERCE DRLAKE CITY, FL 32055
Theodore W..feaster
Feaster Co., Inc.
County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.
Mark A Ganskop
Express Plumbing Inc
James E Tippmann
Mstc Mechanical Contractors Llc
Lewis G Walker
Lewis Walker Roofing Inc
Santos Santiago
Caribbean Fire & Associates, Inc.
County License & State License & Liability Insurance & Workers Comp Expired.
Michael A York
Communications Systems Managment, Inc
Passed: Fire - Plan Review
Inspected by Lance Hill
Passed: Electrical - 1st Underground Rough–In
Inspected by Troy Crews
Cancelled: Building - Footer
Duplicate
Inspected by Emaleigh Williams
Cancelled: Engineering - Setbacks
Passed: Building - Footer
Pad Foundations West Half, And Elevator Pit Foundation. Email Threshold Inspections To Troy.
Passed: Engineering - Setbacks
Elevator Pit Walls
Passed: Electrical - Temporary Service
Release to power company
Remainder Of Foundations And Footer Steel Ground.
Passed: Plumbing/Gas - 1st Underground Rough–In
West Half Of Building Sanitary
Waste Lines East Half Of Building
Passed: Building - Framing
Interior Framing First Three Floors
All Condensate, And Remainder Of Waste Lies 1 Thru 5
Cancelled: Plumbing/Gas - 1st Underground Rough–In
Duplicate Request
Inspected by Anthony Aslan
Passed: Mechanical - Rough In
5th Floor Exhaust Venting, O/a Duct
Failed: Plumbing/Gas - 2nd Rough-In
Could Not Locate Workers For Plumber
Passed: Plumbing/Gas - Rain Leader
Partial Roof Drains Topped Off At Roof
Passed: Electrical - 2nd Rough-In
5 Th Floor Rough In
Framing 5th Floor
Passed: Building - Fire Rated Wall
First Layer Shaft Walls 5th Floor
Passed: Plumbing/Gas - 2nd Rough-In
Passed: Plumbing/Gas - Sanitary
Passed: Plumbing/Gas - Water Pipe
4th Floor Work In Shafts
Guestrooms Only, Hallway And Equipment Rooms Not Complete
5th, 4th, Floor Good To Wrap Fresh Air 3rd Floor Exhaust Duct 1st Floor Partial To Wrap Ducts
Hallways 4 And 5
Third Floor Fresh Air Duct
Passed: Building - Insulation
Working On A Few Soffit Lights.
Rescheduled 2/5/2024:Fire - Underground Main - Hydro
Rescheduled 2/6/2024:Fire - Underground Main - Hydro
Rescheduled 2/7/2024:Fire - Underground Main - Hydro
4 And 5
Insulation, Fire Damper Screws Need Correction
Cancelled: Electrical - Permanent Power
2 Nd Floo
Passed: Electrical - Permanent Power
Main Only Room To Be Locked Out Under Control Of Electrician
2nd Floor Room Ducts
Couple Duct To Tight
Ct Meter Can
Failed: Building - Insulation
Several Areas On Outside Walls Missing Insulation
Check A Couple Of Spots Around Electric And Plumbing, One Left Of Front Door, One In Rear Of Building Around Outlet Box Left Of Electric Room
Need Laundry Insulated supply Drops Conference Rooms
Mastic Refrigerant Lines install Straps On Ducts
Failed: Electrical - 2nd Rough-In
Electrical Not Complete On First Floor Air Handlers
Cancelled: Electrical - 2nd Rough-In
Rooftop
Passed: Electrical - Above Ceiling
5th Floor Hallway
2nd 3rd And 4th Floor Hallways
Rescheduled 9/3/2024:Electrical - 2nd Rough-In
All Guest Rooms 1 Thru 5
Remainder Of Interior First Floor
Plumbing Final
Final Hvac
Certificate-Release Certificate
Fire Final Good Per Rhet Tompkins
Passed: Building - Final
Co Pending Fire Final
Passed: Fire - Fire Final
Inspected by Cpt. Shane Overstreet
Cancelled: City of Lake City Utilities - Lake City Utilities Tap Inspection
Certificate Of Occupancy Was Issued 11/14/24.
Inspected by County Building Department