Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
|
Matt Forsyth |
12/28/2022 |
Release to power company |
|
Matt Forsyth |
12/28/2022 |
Passed: Building - Footer |
|
Matt Forsyth |
1/3/2023 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
1/3/2023 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
2/2/2023 |
Passed: Mechanical - Rough In |
This Inspection Was For A Slab |
Matt Forsyth |
2/9/2023 |
Passed: Building - Slab |
|
Matt Forsyth |
2/13/2023 |
Passed: Building - Vertical Cells/Columns |
|
Matt Forsyth |
2/13/2023 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
3/24/2023 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
3/24/2023 |
Failed: Building - Framing |
Proper Nailing Needed At King Post,two Ply Truss.also Anchor Bolts Both Sides Of Sole Plate Break |
Matt Forsyth |
4/14/2023 |
Passed: Building - Strapping |
|
Matt Forsyth |
4/14/2023 |
Failed: Electrical - 2nd Rough-In |
All Pig Tails In Box Dryer Romex Not Installed In Wall |
Matt Forsyth |
4/14/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
Plumber Putting Nail Plates On |
Matt Forsyth |
4/14/2023 |
Passed: Electrical - 2nd Rough-In |
Item Addressed |
Matt Forsyth |
4/18/2023 |
Failed: Building - Framing |
All Material Covering Lnside Framing Needs To Be Removed |
Matt Forsyth |
4/28/2023 |
Failed: Building - Rated Assembly Fastening |
Not Complete |
Matt Forsyth |
4/28/2023 |
Passed: Building - Framing |
|
Matt Forsyth |
5/3/2023 |
Passed: Building - Strapping |
|
Matt Forsyth |
5/3/2023 |
Cancelled: Building - Insulation |
|
Matt Forsyth |
5/16/2023 |
Cancelled: Mechanical - Rough In |
|
Matt Forsyth |
5/16/2023 |
Passed: Building - Insulation |
|
Matt Forsyth |
5/18/2023 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
5/18/2023 |
Passed: Electrical - Permanent Power |
Need Septic |
Matt Forsyth |
7/26/2023 |
Release to power company |
|
Matt Forsyth |
7/28/2023 |
Septic Release Inspection |
|
Health Dept |
7/28/2023 |
Passed: Building - Monolithic Slab |
|
Matt Forsyth |
9/6/2023 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
9/6/2023 |
Failed: Building - Final |
Blower Door Test Needs Submitted And Reviewed No Water On Fixtures |
Matt Forsyth |
9/12/2023 |
Failed: Building - Final |
No Co Has Been Issued Proof Of Mechanical Air Needed House Has Been Moved Into Need Person Home Before Entering |
Matt Forsyth |
9/19/2023 |
Passed: Building - Final |
|
Matt Forsyth |
10/3/2023 |