Permit Details

Permit Search

Permit

Remodel

355 SW SHORT LN
LAKE CITY, FL 32025

Permit #
000046060
Application #
57365
Status Completed
  1. Submitted Dec 7, 2022
  2. Issued Dec 8, 2022
  3. Expires Oct 22, 2023
  4. Completed Apr 26, 2023

Property

Parcel #
07879-000
Owner
Souza Camille A
Acres
1.81
Subdivision
Lake Forest Unit 2
Zoning
—
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0292D
Type of Structure
House
Commercial or Residential?
Residential
Description of the work being performed:
completion of remodel permit #44956-- see scope of work
Septic#
x-city
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Service Amps
200

Status & Review History

  1. City of Lake City Notified of Application within City of Lake City LC_GAS, LC_WATER, LC_SEWER.
  2. Plan Review - Plumbing Approved
  3. Plan Review - Mechanical Approved
  4. Plan Review - Electrical Approved
  5. Plan Review - Building Approved
  6. Plan Review - Reviewed
  7. Zoning Review - Reviewed
  8. Final Review - Reviewed
  9. Permit Issued

Contractors

This is an owner-builder project.

Inspections

  1. Dec 21, 2022

    Passed: Plumbing/Gas - Water Pipe

    Inspected by Troy Crews

  2. Dec 21, 2022

    Passed: Plumbing/Gas - 2nd Rough-In

    Inspected by Troy Crews

  3. Jan 9, 2023

    Passed: Building - Insulation

    Inspected by Troy Crews

  4. Feb 13, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Sewer Tap Was Checked By City

    Inspected by Troy Crews

  5. Feb 24, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Redy For City Gas To Set Meter.

    Inspected by Troy Crews

  6. Feb 27, 2023

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  7. Feb 27, 2023

    Release to power company

    Inspected by Troy Crews

  8. Feb 28, 2023

    Release to power company

    Changing From Clay To Fpl

    Inspected by Troy Crews

  9. Mar 7, 2023

    Passed: Building - Final

    Semi Permanet.

    Inspected by Troy Crews

  10. Apr 25, 2023

    Passed: Building - Final

    Minimal Standards Met For Living, Owner To Complete Trim, Cabinets, Floor Covering Etc. Trying To Get In After Difficulty With Fire.

    Inspected by Troy Crews

Documents