Permit Details

Permit Search

Permit

New Residential Construction

1903 SW STATE ROAD 47
LAKE CITY, FL 32025

Permit #
000046059
Application #
56876
Status Completed
  1. Submitted Nov 10, 2022
  2. Issued Dec 8, 2022
  3. Expires Jan 8, 2024
  4. Completed Jul 13, 2023

Property

Parcel #
08451-005
Owner
Glover Katherine Millkin, Glover Philip
Acres
1.78
Subdivision
—
Zoning
—
Flood zone
X
District
5

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Minimum Requirement
Finished floor requirement
One foot above the road
Fema map number
22-0892
In floodway
N
This is the construction of a
Single Family Dwelling
Setbacks Front
25'
Setback Side 1
10'
Setback Side 2
10'
Setbacks Rear
15'
Stories
1
Heated Area (Sqft)
2548
Total Area (Sqft)
3555
Building Code Construction Type
IV
Building Code Element
B
Building Code Occupancy Types
Residential
Occupancy Use Title
single family dwelling
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic# (00-0000) or (X00-000)
22-0892
Sealed roof decking options. (Must select one option per FBC 2023 8th Edition)
a minimum 4-inch wide strip of selfadhering polymer-modified bitumen complying with ASTM D1970 or a minimum 3 ¾ - inch wide strip of selfadhering flexible flashing tape complying with AAMA 711, applied over all joints in the roof decking. A felt underlayment complying with ASTM D226 Type II, ASTM D4869 Type Ill or IV, or ASTM D6757, or a synthetic underlayment meeting the performance requirements specified, is required to be applied over the strips/tape over the entire roof.
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified
  4. Point Review - Printed-Online Application
  5. Plan Review - Building Approved
  6. Plan Review - Electrical Approved
  7. Plan Review - Mechanical Approved
  8. Plan Review - Plumbing Approved
  9. Plan Review - Fuel/Gas Approved
  10. Plan Review - Reviewed
  11. Zoning Review - Reviewed
  12. Final Review - Documents Required
  13. Final Review - Reviewed
  14. Final Review - Reviewed
  15. Final Review - Payment Needed
  16. Final Review - Payment Needed
  17. Permit Issued

Contractors

  • Bryan Zecher

    Bryan Zecher Homes Inc

    License
    CBC1257343
    Title
    Building Contractor
    Role
    Contractor
  • Donald R Hollingsworth

    Holly Electric Inc

    License
    EC13005429
    Title
    Electrical
    Role
    Subcontractor
  • Robert Ogles

    Ogles Roofing & Construction Llc

    License
    CCC1328699
    Title
    Cert Roofing
    Role
    Subcontractor

    County License & State License Expired.

  • Cody Barrs

    Barrs Plumbing Inc

    License
    CFC1427145
    Title
    Plumbing Contractor
    Role
    Subcontractor
  • Anthony R Franks

    Lane Heating & Air Llc

    License
    CAC1818631
    Title
    Cert. A/c Class “b”
    Role
    Subcontractor

    County License & State License Expired.

Inspections

  1. Dec 19, 2022

    Passed: Engineering - Setbacks

    Inspected by Anthony Aslan

  2. Dec 19, 2022

    Passed: Electrical - Temporary Service

    Inspected by Anthony Aslan

  3. Dec 19, 2022

    Release to power company

    Inspected by Anthony Aslan

  4. Dec 19, 2022

    Passed: Building - Footer

    Inspected by Anthony Aslan

  5. Jan 20, 2023

    Passed: Plumbing/Gas - 1st Underground Rough–In

    Inspected by Anthony Aslan

  6. Jan 31, 2023

    Passed: Building - Slab

    Inspected by Anthony Aslan

  7. Mar 1, 2023

    Passed: Building - Ext Strapping/Wall Sheathing

    Inspected by Anthony Aslan

  8. Mar 1, 2023

    Passed: Building - Roof Decking

    Inspected by Anthony Aslan

  9. Mar 3, 2023

    Passed: Building - Framing

    E01 Needs More Strapping To Meet Uplift

    Inspected by Anthony Aslan

  10. Mar 17, 2023

    Passed: Electrical - 2nd Rough-In

    Inspected by Anthony Aslan

  11. Mar 17, 2023

    Passed: Plumbing/Gas - 2nd Rough-In

    Need Stud Shoe Vent Pipe

    Inspected by Anthony Aslan

  12. Mar 17, 2023

    Passed: Mechanical - Rough In

    Inspected by Anthony Aslan

  13. Mar 27, 2023

    Passed: Building - Insulation

    Inspected by Anthony Aslan

  14. Jun 1, 2023

    Cancelled: Electrical - Permanent Power

    Inspected by Melissa Garber

  15. Jun 2, 2023

    Passed: Electrical - Permanent Power

    Need Septic Release

    Inspected by Anthony Aslan

  16. Jun 9, 2023

    Release to power company

    Inspected by Melissa Garber

  17. Jun 9, 2023

    Septic Release Inspection

    Inspected by Health Dept

  18. Jul 12, 2023

    Passed: Building - Final

    Inspected by Anthony Aslan

  19. Jul 13, 2023

    Certificate-Release Certificate

    Recv'd Document

    Inspected by Anthony Aslan

Documents