Inspection |
Notes |
Performed By |
Date |
Septic Release Inspection |
|
Health Dept |
10/19/2022 |
Passed: Electrical - Temporary Service |
|
Anthony Aslan |
11/21/2022 |
Release to power company |
|
Anthony Aslan |
11/21/2022 |
Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Emaleigh Williams |
12/28/2022 |
Cancelled: Electrical - 1st Underground Rough–In |
|
Emaleigh Williams |
12/28/2022 |
Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
12/29/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
12/29/2022 |
Passed: Building - Footer |
|
Anthony Aslan |
1/10/2023 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
1/10/2023 |
Passed: Building - Monolithic Slab |
No Ground Wire Need Picture |
Anthony Aslan |
1/10/2023 |
Cancelled: Building - Footer |
Already Passed Inspection |
Emaleigh Williams |
2/9/2023 |
Cancelled: Engineering - Setbacks |
Already Passed Inspection |
Emaleigh Williams |
2/9/2023 |
Cancelled: Building - Monolithic Slab |
Already Passed Inspection |
Emaleigh Williams |
2/9/2023 |
Cancelled: Building - Footer |
|
Emaleigh Williams |
2/13/2023 |
Cancelled: Engineering - Setbacks |
|
Emaleigh Williams |
2/13/2023 |
Cancelled: Engineering - Setbacks |
|
Melissa Garber |
2/13/2023 |
Cancelled: Building - Footer |
|
Melissa Garber |
2/13/2023 |
Cancelled: Building - Footer |
|
Anthony Aslan |
2/14/2023 |
Cancelled: Engineering - Setbacks |
|
Anthony Aslan |
2/14/2023 |
Passed: Building - Footer |
|
Anthony Aslan |
2/16/2023 |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
2/16/2023 |
Passed: Building - Framing |
Need Temporary Fall Protection On Stairs Inside
stairs On Outside Of Build Needs A Hand Rail Installed. |
Anthony Aslan |
8/7/2023 |
Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
10/17/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
10/17/2023 |
Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Anthony Aslan |
10/17/2023 |
Failed: Mechanical - Rough In |
Fresh Air Needs To Be Insulated
kitchen Exhaust Duct Can Not Be Reduced In Size, No Flex Pipe Allowed Must Be Smooth Inside
multiple Ducts Kinked And Not Strapped
have Question About Return For Down Stair System |
Anthony Aslan |
10/17/2023 |
Passed: Mechanical - Rough In |
Need Straps On Supply Flex First Floor |
Anthony Aslan |
10/19/2023 |
Passed: Building - Insulation |
|
Anthony Aslan |
10/26/2023 |
Passed: Electrical - Permanent Power |
|
Gary Pitzer |
1/5/2024 |
Release to power company |
|
Gary Pitzer |
1/5/2024 |
Passed: Building - Final |
|
Anthony Aslan |
2/26/2024 |