Permit Details

Permit Search

Permit

Solar Power System

139 SE LINDEN LOOP
LAKE CITY, FL 32025

Permit #
000045872
Application #
56979
Status Completed
  1. Submitted Nov 1, 2022
  2. Issued Nov 8, 2022
  3. Expires May 17, 2023
  4. Completed Nov 18, 2022

Property

Parcel #
07497-000
Owner
Deland Pamela Sue,
Acres
0.54
Subdivision
Oak Hill Estates Replat
Zoning
RSF/MH-2
Flood zone
X
District
4

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0311D
PV Type
Stand Alone PV System without Batteries- (DC to AC without utility connection)
Grounding
N.E.C. Chapter 690
AC Options
Exposed
AC Options (Cont..)
In Conduit;THWN-2
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Power Company
Florida Power and Light
Residential or Commercial?
Residential
Where are the panels mounted?
Roof Mounted
Service Amps
200

Status & Review History

  1. Application pending.
  2. Application submitted by applicant.
  3. City of Lake City Utilities Notified
  4. Point Review - On Hold-Incomplete
  5. Point Review - Printed-Online Application
  6. Plan Review - Electrical Approved
  7. Plan Review - Building Approved
  8. Plan Review - Reviewed
  9. Zoning Review - Reviewed
  10. Final Review - Reviewed
  11. Final Review - Reviewed
  12. Final Review - Payment Needed
  13. Permit Issued

Contractors

  • Greg Albright

    Freedom Forever Florida Llc

    License
    EC13008056
    Title
    Cert. Electrical
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp & Employees Workers Comp Expired.

Inspections

  1. Nov 17, 2022

    Cancelled: Building - Footer

    Inspected by Troy Crews

  2. Nov 17, 2022

    Cancelled: Engineering - Setbacks

    Inspected by Troy Crews

  3. Nov 17, 2022

    Cancelled: Solar - Thermal Plumbing Final

    Inspected by Troy Crews

  4. Nov 18, 2022

    Passed: Electrical - Permanent Power

    Inspected by Anthony Aslan

  5. Nov 18, 2022

    Release to power company

    Inspected by Anthony Aslan

  6. Nov 18, 2022

    Passed: Solar - Solar Final

    Inspected by Anthony Aslan