| Inspection |
Notes |
Performed By |
Date |
| Passed: Engineering - Initial Driveway |
|
Smith, Blake |
11/18/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
12/13/2022 |
| Passed: Building - Monolithic Slab |
Need To Send Picture Of Ground Wire Prior To Pour. |
Troy Crews |
12/15/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
12/15/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
12/29/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
12/29/2022 |
| Passed: Building - Framing |
|
Anthony Aslan |
1/9/2023 |
| Passed: Building - Strapping |
|
Anthony Aslan |
1/9/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
1/9/2023 |
| Failed: Mechanical - Rough In |
Not Complete |
Anthony Aslan |
1/9/2023 |
| Cancelled: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
1/9/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
1/9/2023 |
| Failed: Plumbing/Gas - Tub Set/Shower Pan |
Need Water In Tubs |
Anthony Aslan |
1/9/2023 |
| Failed: Plumbing/Gas - 2nd Rough-In |
Hall Tub Leaking At Drain |
Anthony Aslan |
1/10/2023 |
| Failed: Building - Insulation |
Not Complete |
Anthony Aslan |
1/12/2023 |
| Failed: Mechanical - Rough In |
Not Complete |
Anthony Aslan |
1/12/2023 |
| Passed: Building - Insulation |
|
Troy Crews |
1/13/2023 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
1/13/2023 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
3/13/2023 |
| Passed: Engineering - Final Driveway |
|
Smith, Blake |
3/28/2023 |
| Release to power company |
|
Melissa Garber |
4/13/2023 |
| Septic Release Inspection |
|
Health Dept |
4/13/2023 |
| Passed: Building - Final |
Protective Insulation On A/c Condenser |
Anthony Aslan |
5/9/2023 |
| Certificate-Release Certificate |
Recv'd Corrections |
Anthony Aslan |
5/19/2023 |