Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

New Residential Construction Permit
Address 523 SW UPSTAGE GLN
LAKE CITY, FL 32024
Parcel #: 09280-151
Acres: 9.52
Owner: Knoll Darren, Knoll Silja
Subdivision: Oaks Of Lake City Phase 1
Zoning: PRRD
Flood Zone: X
District: 5
Application #: 56246
Permit #: 000045827
Related Permit: Culvert: 000045828
Submitted: Friday, August 26, 2022
Issued: Tuesday, November 1, 2022
Expires: Friday, August 18, 2023
Completed: Friday, August 18, 2023
Status: Completed
Septic Release? Yes
Notes:
SURVEYOR LETTER CONFIRMING FINISHED FLOOR OF 75' REQUIRED HOME BEING PLACED ON LOT 52
Job Details
This is the construction of a Single Family Dwelling
Heated Area (Sqft) 3155
Total Area (Sqft) 5147
Stories 1
Building Height 228
Building Code Construction Type V
Building Code Element B
Building Code Occupancy Types Residential
Occupancy Use Title single family dwelling
Setbacks Front 30'
Setback Side 1 25'
Setback Side 2 25'
Setbacks Rear 25'
Septic# (00-0000) or (X00-000) 22-0793
Service Amps 200
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Elevation regulation Subdivision Plat
Finished floor requirement 75'
Requirement needed By Nailing Inspection
Document needed is a Surveyor letter giving the Finished Floor Elevation
Document receieved Yes
Fema map number 12023C0395C
In floodway N
Sealed roof decking options. (Must select one option per FBC 2020 7th Edition) two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified.
Review Notes
8/26/2022 Application pending.
9/28/2022 Point Review - Printed-Online Application NEEDED: *EH APPROVAL
9/28/2022 Point Review - Reviewed NEEDED: *EH APPROVAL
10/3/2022 Plan Review - Corrections Needed NEEDED: **MANUAL J & ENEGRY FORM SQFT DOESN'T MATCH PLANS *EH APPROVAL
10/12/2022 Plan Review - Building Approved NEEDED: *EH APPROVAL
10/12/2022 Plan Review - Electrical Approved NEEDED: *EH APPROVAL
10/12/2022 Plan Review - Mechanical Approved NEEDED: *EH APPROVAL
10/12/2022 Plan Review - Plumbing Approved NEEDED: *EH APPROVAL
10/12/2022 Plan Review - Fuel/Gas Approved NEEDED: *EH APPROVAL
10/12/2022 Plan Review - Reviewed NEEDED: *EH APPROVAL
10/17/2022 Zoning Review - Reviewed NEEDED: *EH APPROVAL
10/18/2022 Final Review - Documents Required NEEDED: *EH APPROVAL
10/18/2022 Final Review - Reviewed
10/18/2022 Final Review - Payment Needed
11/1/2022 Permit Issued Permit #000045827 created and approved.
11/3/2022 Final Review - Corrections Needed NOC IS NOT RECORDED
Contractors
Name/ Business License Title Role
Isaiah Cully
Ic Construction Llc
CBC1259655 Building Contractor Contractor
Cody Barrs
Barrs Plumbing Inc
CFC1427145 Plumbing Contractor Subcontractor
Tyler M Turner
Tmt Roofing Llc
CCC1330410 Cert Roofing Subcontractor
Everton D Ruddock
D&s Lighting Inc
EC13003800 Electrical Contractor Subcontractor
Clinton G Wilson
Wilson Heat & Air Inc
CAC057886 Class B A/c Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Engineering - Initial Driveway Smith, Blake 11/4/2022
Passed: Building - Footer Troy Crews 11/9/2022
Passed: Engineering - Setbacks Troy Crews 11/9/2022
Passed: Electrical - Temporary Service Troy Crews 11/9/2022
Release to power company Troy Crews 11/9/2022
Rescheduled 12/30/2022:Plumbing/Gas - 1st Underground Rough–In Troy Crews 12/30/2022
Failed: Plumbing/Gas - 1st Underground Rough–In No Water Test Call Back In With Slab Must Be Full For Slab Inspection. Troy Crews 12/30/2022
Failed: Building - Slab Plumbing Not Requested And No Water Test On Plumbing. Troy Crews 1/3/2023
Passed: Plumbing/Gas - 1st Underground Rough–In Troy Crews 1/5/2023
Passed: Building - Slab Water Test On Plumbing Now. Troy Crews 1/5/2023
Failed: Building - Framing Not Ready Gary Pitzer 3/10/2023
Failed: Mechanical - Rough In Not. Ready Gary Pitzer 3/10/2023
Failed: Plumbing/Gas - 2nd Rough-In Not Ready Gary Pitzer 3/10/2023
Failed: Building - Framing Missing Truss Bracing In Loft Area Above Garage Gary Pitzer 3/27/2023
Passed: Electrical - 2nd Rough-In Gary Pitzer 3/27/2023
Failed: Mechanical - Rough In 1.duct In Loft Araa Above Garage Crushed, 2 Exhaust Vent Pipe In Masted Bath Need Extra Pipe Remove Gary Pitzer 3/27/2023
Passed: Plumbing/Gas - 2nd Rough-In Gary Pitzer 3/27/2023
Passed: Mechanical - Rough In Gary Pitzer 4/4/2023
Passed: Building - Framing Gary Pitzer 4/4/2023
Failed: Building - Insulation Must Complete Mechanicals And Framing Prior To Insulation Troy Crews 4/6/2023
Passed: Building - Insulation Gary Pitzer 4/6/2023
Passed: Electrical - Permanent Power Gary Pitzer 6/23/2023
Release to power company Gary Pitzer 6/23/2023
Septic Release Inspection Health Dept 7/19/2023
Passed: Engineering - Final Driveway Smith, Blake 7/21/2023
Failed: Building - Final Handrail To Up Second Floor Does Not Extend Full Length Of Stairs, Need Outlet Added To Counter Top Under Window, Kitchen Outlets Need Arc-fault Protection, No Shut Off Valve On Gas Cook Stove. This For House Only Gary Pitzer 8/14/2023
Rescheduled 8/18/2023:Building - Final Gary Pitzer 8/15/2023
Passed: Building - Final Gary Pitzer 8/18/2023
Documents
File Name Date File Size
Architectural Plans 20220826 105919.pdf 2023.12.24 4.02MB
Truss Engineering 20220829 144558.pdf 2023.12.24 996.55kB
Certificate Of Occupancy 20230818.pdf 2023.12.24 53.74kB
Sealed S4.pdf 2023.12.24 1.16MB
Reviewed Architectural Plans 56246 2022-10-03 14.33.33.401.pdf 2023.12.24 4.10MB
Manual J.pdf 2023.12.24 213.68kB
Reviewed Truss Engineering 56246 2022-10-03 14.33.32.855.pdf 2023.12.24 1.17MB
Lidar 56246 2022-10-17 13.24.46.360.pdf 2023.12.24 133.24kB
Property Appraiser Parcel Details Printed Page 20220826 105927.pdf 2023.12.24 1.40MB
Energy Code Forms.pdf 2023.12.24 64.72kB
Termite Certificate_final 20230809 100642.pdf 2023.12.24 246.15kB
Sealed S1.pdf 2023.12.24 1.32MB
Residential Or Commercial Checklist 20220826 105640.pdf 2023.12.24 857.25kB
Termite Treatment_initial 20230809 100643.pdf 2023.12.24 246.15kB
Win_20230103_16_08_18_pro 2023-01-03 16.09.11.216.jpg 2023.12.24 175.57kB
523 Sw Upstage Gln 2022-08-29 14.05.21.958.pdf 2023.12.24 168.52kB
Recorded Notice Of Commencement 20221104 092827.pdf 2023.12.24 110.02kB
Knoll Eh.pdf 2023.12.24 1.44MB
Recorded Deed 20220826 105000.pdf 2023.12.24 742.22kB
Owner And Contractor Signature Page 20220826 153939.pdf 2023.12.24 772.53kB
Power Release-electrical-permanent Power 20230623.pdf 2023.12.24 39.06kB
Blower Door Test Results 20230809 103508.pdf 2023.12.24 907.84kB
Oaks_of_lake_city_phs1 (1).pdf 2023.12.24 6.74MB
Subcontractor Form 20220826 105642.pdf 2023.12.24 781.23kB
45827 Letter For Outlet.pdf 2023.12.24 148.25kB
Original Permit 20221101.pdf 2023.12.24 46.29kB
Sealed S3.pdf 2023.12.24 2.73MB
Power Release-electrical-temporary Service 20221109.pdf 2023.12.24 38.91kB
Site Plan 20220826 105930.pdf 2023.12.24 111.58kB
Recorded Notice Of Commencement 20221201 121025.pdf 2023.12.24 110.02kB
Surveyor Letter Giving The Finished Floor Elevation 20230306 103552.pdf 2023.12.24 153.04kB
Sealed S2.pdf 2023.12.24 1.45MB