Inspection |
Notes |
Performed By |
Date |
Cancelled: Building - Footer |
|
Melissa Garber |
11/14/2022 |
Cancelled: Engineering - Setbacks |
|
Melissa Garber |
11/14/2022 |
Passed: Building - Footer |
|
Matt Forsyth |
11/15/2022 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
11/15/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Drains And Water Line (cpvc) |
Gary Pitzer |
1/13/2023 |
Passed: Building - Slab |
|
Anthony Aslan |
1/18/2023 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
2/23/2023 |
Passed: Building - Wall Sheathing |
|
Anthony Aslan |
2/23/2023 |
Failed: Building - Framing |
Headers Over Doors And Windows Not Built To Plan Anchor Bolts Missing No Truss Engineering |
Matt Forsyth |
2/28/2023 |
Failed: Building - Strapping |
Need Gable Strapping |
Matt Forsyth |
2/28/2023 |
Passed: Electrical - Temporary Service |
Windows Were Checked And Inspected |
Matt Forsyth |
3/1/2023 |
Release to power company |
|
Matt Forsyth |
3/1/2023 |
Rescheduled 3/16/2023:Building - Framing |
|
Matt Forsyth |
3/7/2023 |
Passed: Building - Strapping |
|
Matt Forsyth |
3/7/2023 |
Failed: Building - Framing |
Need Engineer Letter On Header Build |
Matt Forsyth |
3/16/2023 |
Passed: Building - Framing |
Doc Rec |
Matt Forsyth |
3/20/2023 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
3/22/2023 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
3/22/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
3/22/2023 |
Passed: Building - Insulation |
Fresh Air Duct Connected To Return In Bedroom Not Main Duct.
if Bolwer Door Is Less Than 3 Ach, An Automatic Damper Must Be Installed. |
Anthony Aslan |
3/31/2023 |
Septic Release Inspection |
|
Health Dept |
4/5/2023 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
5/19/2023 |
Release to power company |
|
Matt Forsyth |
5/19/2023 |
Passed: Building - Final |
|
Anthony Aslan |
7/21/2023 |