| Passed: Electrical - 1st Underground Rough–In |
Rough In Underground For Charging Stations. |
Troy Crews |
10/5/2023 |
| Passed: Building - Footer |
Chargers Footings. |
Troy Crews |
10/10/2023 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
10/10/2023 |
| Cancelled: Building - Monolithic Slab |
|
Troy Crews |
10/10/2023 |
| Cancelled: Engineering - Setbacks |
|
Troy Crews |
10/10/2023 |
| Passed: Building - Slab |
|
Troy Crews |
10/10/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
11/29/2023 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
11/29/2023 |
| Release to power company |
|
Troy Crews |
11/29/2023 |
| Passed: Building - Final |
|
Troy Crews |
12/20/2023 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
12/20/2023 |
| Release to power company |
|
Troy Crews |
12/20/2023 |