| Inspection |
Notes |
Performed By |
Date |
| Septic Release Inspection |
|
Health Dept |
7/22/2022 |
| Passed: Building - Footer |
|
Matt Forsyth |
9/27/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
9/27/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Waste And Water |
Matt Forsyth |
11/28/2022 |
| Passed: Building - Slab |
|
Matt Forsyth |
12/7/2022 |
| Cancelled: Building - Slab |
|
Matt Forsyth |
12/7/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
12/21/2022 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
12/21/2022 |
| Passed: Building - Strapping |
|
Matt Forsyth |
12/29/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
1/31/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/31/2023 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
1/31/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/31/2023 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
Tub Water Tested |
Matt Forsyth |
1/31/2023 |
| Rescheduled 2/6/2023:Building - Insulation |
|
Matt Forsyth |
2/3/2023 |
| Passed: Building - Insulation |
Walls Only Condensate Line For Air Handler Not Run |
Matt Forsyth |
2/6/2023 |
| Failed: Electrical - Permanent Power |
Dead Cover Of Panel Not Fitting Properly Around Breakers |
Matt Forsyth |
4/6/2023 |
| Failed: Electrical - Permanent Power |
Sub Contractors Need Updates Done Prior To Further Mechanical Inspections |
Troy Crews |
4/12/2023 |
| Cancelled: Electrical - Permanent Power |
|
Matt Forsyth |
4/13/2023 |
| Passed: Electrical - Permanent Power |
|
Matt Forsyth |
4/14/2023 |
| Release to power company |
|
Matt Forsyth |
4/14/2023 |
| Passed: Building - Final |
Need Proper Drainage Around House |
Matt Forsyth |
4/27/2023 |
| Passed: Building - Final |
|
Matt Forsyth |
5/1/2023 |