Roof Replacement or Repair
Permit
| Application #: | 56375 |
| Permit #: |
000045389 |
| Related Permit: |
|
| Submitted: | Wednesday, September 7, 2022 |
| Issued: | Thursday, September 8, 2022 |
| Expires: | Tuesday, September 20, 2022 |
| Completed: | Tuesday, September 20, 2022 |
| Status: |
Completed |
| Septic Release? |
N/A |
Notes
PICS AND AFFIDAVIT REC'D
Job Details
| Finished floor requirement |
|
| Fema map number |
12023C0195D |
| Type Roofing Job |
Replacement - Tear off Existing and Replace |
| Further Job Details (Explain if decking is being replaced and or Repairs are being done.) |
Flat re-roof plus some fascia replacement. |
| Type of structure |
Commercial Building |
| Commercial or Residential |
Commercial |
| Roof Area (for this job) Sq Ft |
736 |
| No. of Stories |
1 |
| Roof Pitch |
Less than 2:12 |
| Is the existing roof being removed? |
Yes |
| Type of New Roofing Product |
Roll Roofing |
| Florida Product Approval Number |
FL2533-R28 |
| Product Manufacturer |
CertainTeed |
| Product Description |
Modified Bitumen Roof System |
| Building Code Edition |
2020 Florida Building Code 7th Edition and Florida Statute 553.844 |
| Sealed roof decking options: (Must select an option.) |
two layers of felt underlayment comply ASTM 0226 Type II or ASTM D4869 Type Ill or IV, or two layers of a synthetic underlayment meeting the performance requirements specified, lapped and fastened as specified. |
| Ventilation: |
Unvented |
| Flashing: |
Replace All |
| Drip Edge: |
Replace All |
| Valley Treatment: |
New Metal |
| Any cable and/or race-way wiring located on or within the roof assembly? |
No |
Review Notes
| 9/7/2022 |
Application pending. |
| 9/7/2022 |
Point Review - Processing |
| 9/7/2022 |
Final Review - Documents Required |
| 9/7/2022 |
Final Review - Reviewed |
| 9/7/2022 |
Final Review - Payment Needed |
| 9/8/2022 |
Permit Issued |
Contractors
| Name / Business |
License |
Title |
Role |
Nicholas D Carlucci Florida Roof Masters Llc
|
CCC1331527 |
Cert. Roofing |
Contractor |
Inspections
| Inspection |
Notes |
Performed By |
Date |
| Cancelled: Re-Roof - In Progress |
|
Anthony Aslan |
9/12/2022 |
| Failed: Re-Roof - In Progress |
No In Progress |
Anthony Aslan |
9/14/2022 |
| Passed: Re-Roof - In Progress |
|
Anthony Aslan |
9/15/2022 |
| Cancelled: Re-Roof - In Progress |
In Progress Already Completed |
Emaleigh Williams |
9/15/2022 |
| Passed: Re-Roof - Final |
Campground Office |
Matt Forsyth |
9/20/2022 |