Inspection |
Notes |
Performed By |
Date |
Passed: Electrical - Temporary Service |
Receptacles Used Will Be Ground Fault Protected |
Matt Forsyth |
10/4/2022 |
Release to power company |
|
Matt Forsyth |
10/4/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Compaction Test Needed |
Matt Forsyth |
10/4/2022 |
Passed: Building - Slab |
Fiber Mesh Concrete Being Used |
Matt Forsyth |
10/11/2022 |
Release to power company |
Changed From Fpl To Sve |
Melissa Garber |
10/18/2022 |
Cancelled: Building - Roof Decking |
|
Matt Forsyth |
11/2/2022 |
Failed: Building - Wall Sheathing |
All Nails Missing Framing Members Must Be Removed And Re Nailed All 8 Foot Blocking On Wall Sheathing Must Be Installed The Perimeter Wall Was Missing Several Nails Needs To Be Gone Back Over |
Matt Forsyth |
11/2/2022 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
11/4/2022 |
Failed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
3/1/2023 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
3/1/2023 |
Failed: Building - Framing |
Call Matt |
Matt Forsyth |
3/1/2023 |
Cancelled: Building - Wall Sheathing |
|
Matt Forsyth |
4/11/2023 |
Passed: Building - Framing |
|
Matt Forsyth |
4/11/2023 |
Failed: Electrical - 2nd Rough-In |
Pigtails Need To Be Inside Box |
Matt Forsyth |
4/11/2023 |
Failed: Mechanical - Rough In |
Black Tape Not Listed For Duct |
Matt Forsyth |
4/11/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
4/11/2023 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
4/13/2023 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
4/13/2023 |
Cancelled: Building - Insulation |
|
Matt Forsyth |
4/20/2023 |
Passed: Building - Insulation |
|
Matt Forsyth |
4/25/2023 |
Passed: Engineering - Spot Check |
Need Conduit Run Underground For Permanent Power |
Matt Forsyth |
11/9/2023 |
Passed: Electrical - Permanent Power |
Garage Doors Were Being Installed Need Septic Release |
Matt Forsyth |
1/25/2024 |
Release to power company |
|
Melissa Garber |
2/21/2024 |
Septic Release Inspection |
|
Health Dept |
2/21/2024 |
Passed: Engineering - Spot Check |
Needed Us To Look To See If Anything Would Hold Up Co. Several Items Remain Incomplete, No Testing On Electric Done. Few Lights Missing. No Lifemsafty Tested Or Given,
. No Inspection Completed On This Trip. |
Gary Pitzer |
7/18/2024 |
Rescheduled 8/7/2024:Building - Final |
|
Troy Crews |
8/6/2024 |
Failed: Building - Final |
Permit Holders Responsibility To Have Access To Inspection |
Matt Forsyth |
8/7/2024 |
Passed: Building - Final |
|
Matt Forsyth |
8/8/2024 |