Inspection |
Notes |
Performed By |
Date |
Electrical -1st Underground Rough–In |
Passed By Mwinburn |
Private Provider |
12/7/2022 |
Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Melissa Garber |
12/9/2022 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Melissa Garber |
12/9/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Passed By Mwinburn |
Private Provider |
12/9/2022 |
Passed: Building - Slab |
Passed By Mwinburn
no Footer/setback Inspection, No Co Until Confirmation |
Private Provider |
12/9/2022 |
Building-Roof Decking |
Passed By Mmcelroy |
Private Provider |
12/14/2022 |
Building-Ext Strapping/Wall Sheathing |
Passed By Mmcelroy |
Private Provider |
12/14/2022 |
Building-Strapping |
Roof Dry In, House Wrap And Window Attachment-- Passed By Mmcelroy |
Private Provider |
12/14/2022 |
Building-Framing |
Passed By Mwinburn |
Private Provider |
2/16/2023 |
Mechanical-Rough In |
Passed By Mwinburn |
Private Provider |
2/16/2023 |
Electrical -2nd Rough-In |
Passed By Mwinburn |
Private Provider |
2/16/2023 |
Plumbing/Gas-2nd Rough-In |
Passed By Mwinburn |
Private Provider |
2/16/2023 |
Building-Insulation |
Passed By Mwinburn |
Private Provider |
3/3/2023 |
Electrical -Permanent Power |
Passed By Sgreen |
Private Provider |
8/17/2023 |
Cancelled: Building - Footer |
|
Melissa Garber |
8/21/2023 |
Cancelled: Engineering - Setbacks |
|
Melissa Garber |
8/21/2023 |
Cancelled: Plumbing/Gas - 1st Underground Rough–In |
|
Melissa Garber |
8/21/2023 |
Release to power company |
|
Melissa Garber |
8/22/2023 |
Mechanical-Rough In |
Mechanical Final-- Passed By Sgreen |
Private Provider |
8/28/2023 |
Electrical -Permanent Power |
Electrical Final-- Passed By Sgreen |
Private Provider |
8/28/2023 |
Plumbing/Gas-2nd Rough-In |
Plumbing Final-- Passed By Sgreen |
Private Provider |
8/28/2023 |
Building-Final |
Passed By Sgreen |
Private Provider |
8/28/2023 |
Certificate-Release Certificate |
|
Troy Crews |
8/28/2023 |