| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
Concrete Base Put Down To Stop Ground Water, Structural Footers To Follow. |
Troy Crews |
9/1/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
9/1/2022 |
| Passed: Building - Footer |
|
Troy Crews |
9/8/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
9/8/2022 |
| Passed: Building - Footer |
Pad Foundations For Canopies Oversized To 8 Foot |
Troy Crews |
9/15/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
9/15/2022 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
9/28/2022 |
| Release to power company |
|
Troy Crews |
9/28/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
9/28/2022 |
| Passed: Electrical - 1st Underground Rough–In |
Rough In Underground, Dont See Any Wiring For Grounding System. |
Troy Crews |
10/10/2022 |
| Cancelled: Building - Slab |
|
Troy Crews |
10/24/2022 |
| Passed: Building - Slab |
|
Troy Crews |
10/26/2022 |
| Release to power company |
Originally Released On 9/28, Re Releasing Due To Fpl Claiming It Wasn't Received. |
Melissa Garber |
12/21/2022 |
| Passed: Building - Monolithic Slab |
Slab For Vacuum Building |
Troy Crews |
12/27/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
12/27/2022 |
| Passed: Electrical - Temporary Service |
Meter Setup For 120 Volts |
Troy Crews |
12/27/2022 |
| Release to power company |
|
Troy Crews |
12/27/2022 |
| Passed: Electrical - 1st Underground Rough–In |
Conduit From Main Building To Vacuum Building And To Canopies For Lights |
Troy Crews |
1/20/2023 |
| Passed: Electrical - 1st Underground Rough–In |
Pay Island Piping. |
Troy Crews |
1/25/2023 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
3/29/2023 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
4/20/2023 |
| Release to power company |
|
Troy Crews |
4/20/2023 |
| Cancelled: Building - Pre-Certificate Public Works Inspection |
|
Troy Crews |
5/10/2023 |
| Certificate-Release Certificate |
Sign Added To Electrical Room |
Troy Crews |
5/11/2023 |
| Passed: Building - Final |
Co Pending Electric Room Placard |
Troy Crews |
5/11/2023 |