Inspection |
Notes |
Performed By |
Date |
Septic Release Inspection |
|
Health Dept |
8/9/2022 |
Failed: Plumbing/Gas - 1st Underground Rough–In |
Need Noc Posted Also Permit Posted Also Need Compaction Test Water Had Leaked Out Of Stand Pipe |
Matt Forsyth |
8/12/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Still Looking For Compaction Test |
Matt Forsyth |
8/19/2022 |
Cancelled: Building - Footer |
|
Matt Forsyth |
8/31/2022 |
Cancelled: Engineering - Setbacks |
|
Matt Forsyth |
8/31/2022 |
Failed: Building - Monolithic Slab |
Contractor Sending Me A Picture Of A Spread Footing Before They Pour |
Matt Forsyth |
8/31/2022 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
8/31/2022 |
Cancelled: Building - Slab |
|
Matt Forsyth |
8/31/2022 |
Passed: Building - Monolithic Slab |
Spread Footing Pic Was Good Compaction Test In Pemit File |
Matt Forsyth |
9/1/2022 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
9/1/2022 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
9/16/2022 |
Passed: Building - Roof Decking |
|
Matt Forsyth |
9/16/2022 |
Passed: Building - Framing |
Need Exterior Door Installed Before Insulating |
Matt Forsyth |
10/13/2022 |
Passed: Electrical - 2nd Rough-In |
|
Matt Forsyth |
10/13/2022 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
10/13/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
Tubs Water Tested |
Matt Forsyth |
10/13/2022 |
Passed: Building - Insulation |
|
Matt Forsyth |
10/20/2022 |
Failed: Electrical - Permanent Power |
Need Conduit Pipe Run To Meter Can |
Matt Forsyth |
12/1/2022 |
Cancelled: Electrical - Temporary Service |
|
Matt Forsyth |
12/1/2022 |
Cancelled: Electrical - Permanent Power |
|
Matt Forsyth |
12/6/2022 |
Passed: Electrical - Permanent Power |
|
Matt Forsyth |
12/8/2022 |
Release to power company |
|
Matt Forsyth |
12/8/2022 |
Cancelled: Electrical - Temporary Service |
|
Matt Forsyth |
12/8/2022 |
Failed: Building - Final |
Drain Pan Water Heater Piped To Outside. Water To Fixtures Turned On Mb Receptacle Needs To Be Checked At Sink |
Matt Forsyth |
12/22/2022 |
Passed: Building - Final |
Items Have Been Addressed |
Matt Forsyth |
12/28/2022 |