Inspection |
Notes |
Performed By |
Date |
Passed: Building - Footer |
Need Permit Box On Job Fr Documents |
Matt Forsyth |
8/18/2022 |
Passed: Engineering - Setbacks |
|
Matt Forsyth |
8/18/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
9/7/2022 |
Passed: Building - Slab |
Fiber Mesh Concrete Being Used |
Matt Forsyth |
9/14/2022 |
Passed: Building - Wall Sheathing |
|
Matt Forsyth |
9/22/2022 |
Failed: Building - Framing |
3 Ply Trusses Not Nailed Properly Also Fire Blocking In Several Spots Mostly Kitchen Area |
Matt Forsyth |
11/7/2022 |
Failed: Building - Framing |
Need Proper Portal Hold Down In The Garage |
Matt Forsyth |
12/15/2022 |
Failed: Electrical - 2nd Rough-In |
Receptacles Missing On Kitchen Countertop |
Matt Forsyth |
12/15/2022 |
Passed: Mechanical - Rough In |
|
Matt Forsyth |
12/15/2022 |
Failed: Plumbing/Gas - 2nd Rough-In |
Missing A Few Nail Plates On Vent Stacks |
Matt Forsyth |
12/15/2022 |
Passed: Building - Insulation |
|
Matt Forsyth |
1/4/2023 |
Passed: Electrical - 2nd Rough-In |
Under Kitchen Cabinet Receptacles |
Matt Forsyth |
1/4/2023 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/4/2023 |
Failed: Building - Framing |
Need Letter For Alt.method On Portal Holdown |
Matt Forsyth |
1/4/2023 |
Cancelled: Building - Insulation |
|
Matt Forsyth |
1/5/2023 |
Cancelled: Building - Framing |
|
Matt Forsyth |
1/5/2023 |
Cancelled: Electrical - 2nd Rough-In |
|
Matt Forsyth |
1/5/2023 |
Cancelled: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
1/5/2023 |
Passed: Building - Framing |
Letter Received From Engineer |
Matt Forsyth |
1/6/2023 |
Septic Release Inspection |
|
Health Dept |
2/1/2023 |
Passed: Electrical - Permanent Power |
Septic Needed |
Matt Forsyth |
3/15/2023 |
Release to power company |
|
Melissa Garber |
3/16/2023 |
Rescheduled 3/31/2023:Building - Final |
|
Matt Forsyth |
3/30/2023 |
Passed: Building - Final |
|
Matt Forsyth |
3/31/2023 |