| Inspection |
Notes |
Performed By |
Date |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
Water Supply Needs To Be Under Pressure At Slab Inspection. Need Permit And Document Box On Site. Will Need Compaction Test |
Matt Forsyth |
10/10/2022 |
| Passed: Building - Monolithic Slab |
Compaction Received |
Matt Forsyth |
10/13/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
10/13/2022 |
| Passed: Electrical - 1st Underground Rough–In |
|
Matt Forsyth |
10/13/2022 |
| Passed: Building - Footer |
|
Matt Forsyth |
10/13/2022 |
| Cancelled: Engineering - Setbacks |
|
Matt Forsyth |
10/13/2022 |
| Rescheduled 10/20/2022:Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
10/19/2022 |
| Cancelled: Building - Ext Strapping/Wall Sheathing |
|
Emaleigh Williams |
10/19/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Matt Forsyth |
10/21/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
10/24/2022 |
| Passed: Building - Framing |
Item Addressed |
Matt Forsyth |
10/31/2022 |
| Passed: Electrical - 2nd Rough-In |
Dryer Plug Needs Four Wires |
Matt Forsyth |
11/9/2022 |
| Passed: Mechanical - Rough In |
|
Matt Forsyth |
11/9/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Matt Forsyth |
11/9/2022 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
11/9/2022 |
| Release to power company |
|
Matt Forsyth |
11/9/2022 |
| Passed: Building - Insulation |
Insulation For Walls Only |
Matt Forsyth |
11/17/2022 |
| Passed: Engineering - Initial Driveway |
|
Smith, Blake |
1/12/2023 |
| Passed: Electrical - Permanent Power |
Need Septic And Driveway Final |
Troy Crews |
2/17/2023 |
| Cancelled: Engineering - Final Driveway |
|
Emaleigh Williams |
2/22/2023 |
| Passed: Engineering - Final Driveway |
|
Smith, Blake |
3/17/2023 |
| Release to power company |
|
Melissa Garber |
3/23/2023 |
| Septic Release Inspection |
|
Health Dept |
3/23/2023 |
| Cancelled: Building - Final |
|
Emaleigh Williams |
5/9/2023 |
| Cancelled: Building - Pre-Certificate Public Works Inspection |
|
Emaleigh Williams |
5/9/2023 |
| Passed: Building - Final |
Need Blower Door Test And Final Termite Treatment |
Matt Forsyth |
5/10/2023 |
| Certificate-Release Certificate |
|
Matt Forsyth |
5/26/2023 |