| Septic Release Inspection |
|
Health Dept |
6/3/2022 |
| Passed: Building - Framing |
Floor Framing Only, Anchor Lenght Need To Be Verified Due To Floor Raised. |
Anthony Aslan |
8/4/2022 |
| Failed: Building - Framing |
Not Ready, Need All Framing And Sheating Completed |
Anthony Aslan |
8/18/2022 |
| Failed: Building - Framing |
Not Built To Plans, Nails Missing, Blocking Missing.
not Ready On Next Inspection $50 Fee Will Be Assessed.
porch Can Be Sheathed |
Anthony Aslan |
9/15/2022 |
| Failed: Building - Wall Sheathing |
Missing Nails Need To Check Nailong |
Anthony Aslan |
9/15/2022 |
| Cancelled: Building - Framing |
|
Anthony Aslan |
9/28/2022 |
| Cancelled: Building - Wall Sheathing |
|
Anthony Aslan |
9/28/2022 |
| Passed: Building - Wall Sheathing |
Edge On Roof Right Front |
Anthony Aslan |
9/28/2022 |
| Failed: Building - Framing |
Stairs Need 6'8" Head Room Only Have 5'7" At Landing. |
Anthony Aslan |
9/28/2022 |
| Passed: Building - Final |
|
Anthony Aslan |
12/2/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
12/2/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
12/2/2022 |
| Passed: Building - Framing |
Stairs Corrected |
Anthony Aslan |
12/2/2022 |
| Cancelled: Building - Final |
|
Anthony Aslan |
12/5/2022 |
| Cancelled: Electrical - Permanent Power |
|
Anthony Aslan |
12/5/2022 |