Columbia County is committed to ensuring accessibility to this website regardless of disability. If anyone encounters a feature on this website that is inaccessible due to a disability, please contact the County Manger’s Office and the Columbia County Board of County Commissioners at (386) 758-1005. You may also email that office at patrick_weaver@columbiacountyfla.com and provide a brief description of the inaccessible feature. The County will either correct the inaccessible feature or, if correction is not possible due to technical limitations, provide the desired information through alternative means.

Skip to content

Columbia County, FL | Permit Details

Additions Permit

Address 4772 NW US HIGHWAY 41
LAKE CITY, FL 32055
Parcel #: 02063-000
Acres: 1.38
Owner: Johnson & Johnson, Inc
Subdivision:
Zoning: CHI
Flood Zone: X
District: 1
Application #: 50241
Permit #: 000044701
Related Permit:
Submitted: Wednesday, August 11, 2021
Issued: Friday, June 17, 2022
Expires: Thursday, May 4, 2023
Completed: Thursday, May 4, 2023
Status: Completed
Septic Release? Yes
Notes:
SITE & DEVELOPMENT PLAN APPROVED SDP21 09 ADDITION MUST MEET THE FINISHED FLOOR OF THE EXISTING BUILDING FUEL SERVICE AREA EXPANSION #41533
Job Details
Elevation regulation Minimum Requirement
Finished floor requirement (EXISTING STORE IS 124.79') Meet existing structure
Document needed is NA
Fema map number 12023C0285D
Is this an addition for commercial or residential use? Commercial
Description of addition: Cooler and remodel of interior/exterior of gas station
Total Estimated Cost 1000000.00
Heated Area (Sqft) 9000
Total Area (Sqft) 13166
Stories 1
Building Height 23
Select driveway access to property: Existing Drive
Fire sprinklers? Yes
Building Code Construction Type V
Building Code Occupancy Types Mercantile
Building Code Element B
Occupancy Use Title mercantile
Setbacks Front 20'
Setback Side 1 5'
Setback Side 2 5'
Setback Rear 15'
Septic# (00-0000) or (X00-000) x22
Dev Permit # F023-
Building Code Edition 2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Sealed roof decking options. (Must select one.) Other (explain)
Sealed roof decking explanation for other option. Polyvinyl Chloride (PVC) Roofing System
Review Notes
8/11/2021 Application pending.
8/12/2021 Application Converted Application was converted from Additions to Remodel
8/12/2021 Point Review - Printed-Online Application JUSTIN: THIS ISN'T AN ADDITION. WE WILL CONVERT TO A COMMERCIAL REMODEL AS INDICATED AS DECSRIPTION OF WORK. PLEASE UPLOAD THE REMAINDER: SUB-VF - SIGNATURE FROM DAVID WOOD KINJAC CORPORATION - SUNBIZ.ORG - DETAIL ENTITY PAGE SHOWING ACTIVE STATUS/
8/12/2021 Application Converted Application was converted from Remodel to Additions
8/12/2021 Zoning Review - On Hold-Incomplete JUSTIN: OKAY, CORRECTION - I WAS JUST INFORMED BY MY DIRECTOR HE SPOKE WITH YOU ABOUT THIS. HE SAID IT'S INDEED AN ADDITION. - WE'RE CHECKING - TROY CREWS...-CONFIRMED THIS PROJECT WILL REQUIRE A SITE & DEVELOPMENT APPROVAL THROUGH ZONING DEPT. PLEASE UPLOAD THE REMAINDER: CURRENT CERTIFICATE OF LIABILTY -- JM PHELPS CONSTRUCTION. SUB-VF - SIGNATURE FROM DAVID WOOD KINJAC CORPORATION - SUNBIZ.ORG - DETAIL ENTITY PAGE SHOWING ACTIVE STATUS KINJAC PHONE NUMBER - EDIT AND SAVE CHANGES. UPON FURTHER REVIEW, THE EXISTING CONSTRUCTION IS NOT IN COMPLIANCE WITH THE APPROVED SITE AND DEVELOPMENT PLAN. FURTHER, PROPOSED ADDITION HAS NOT BEEN APPROVED VIA SITE AND DEVELOPMENT PLAN. SITE PLAN SUBMITTED WITH APPLICATION FOR BUILDING PERMIT IS NOT IN COMPLIANCE WITH THE LAND DEVELOPMENT REGULATIONS AND VIOLATES ADA REQUIREMENTS FOR HANDICAP PARKING AND ACCESS. IT IS RECOMMENDED THAT ALL SITE CONSTRUCTION CEASE UNTIL A SITE AND DEVELOPMENT PLAN IS SUBMITTED AND APPROVED. OTHERIWSE, APPLICANT MAY BE LIABLE FOR REMOVAL OF NEWLY INSTALLED ASPHALT OR IMPERVIOUS SURFACING, ADDITIONAL ENGINEERING, AND OTHER CONSTRUCTION RELATED COSTS.
9/20/2021 Zoning Review - Reviewed PLEASE UPLOAD THE REMAINDER: CURRENT CERTIFICATE OF LIABILTY -- JM PHELPS CONSTRUCTION. SUB-VF - SIGNATURE FROM DAVID WOOD
10/26/2021 Plan Review - Documents Required NEED ENGINEERING STRUCTURAL PLANS, ENERGY CALCULATIONS, COMMERCIAL CHECKLIST FILLED OUT, PRODUCT APPROVAL #S FOR WINDOWS DOORS ROOFING ETC. ALSO NEED CURRENT PHASE COMPLETED ROAD WORK ETC.
10/26/2021 Plan Review - Documents Required NEED ENGINEERING STRUCTURAL PLANS, ENERGY CALCULATIONS, COMMERCIAL CHECKLIST FILLED OUT, PRODUCT APPROVAL #S FOR WINDOWS DOORS ROOFING ETC. ALSO NEED CURRENT PHASE COMPLETED ROAD WORK ETC.
11/5/2021 Plan Review - Documents Required NEED ENGINEERING STRUCTURAL PLANS, ENERGY CALCULATIONS, COMMERCIAL CHECKLIST FILLED OUT, PRODUCT APPROVAL #S FOR WINDOWS DOORS ROOFING ETC. ALSO NEED CURRENT PHASE COMPLETED ROAD WORK ETC. CURRENT PHASE NEEDS TO BE COMPLETE PRIOR TO BUILDING PERMIT FOR ADDITION TC 11-5-21
11/5/2021 Plan Review - Documents Required NEED: ENERGY CALCULATIONS, COMMERCIAL CHECKLIST FILLED OUT, NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21
11/30/2021 Plan Review - Plumbing Approved NEED: COMMERCIAL CHECKLIST FILLED OUT, NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C.
11/30/2021 Plan Review - Mechanical Approved NEED: COMMERCIAL CHECKLIST FILLED OUT, NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C.
11/30/2021 Plan Review - Electrical Approved NEED: COMMERCIAL CHECKLIST FILLED OUT, NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C.
11/30/2021 Plan Review - Building Approved NEED: COMMERCIAL CHECKLIST FILLED OUT, NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C.
11/30/2021 Plan Review - Documents Required NEED: COMMERCIAL CHECKLIST FILLED OUT, NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C.
11/30/2021 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C.
12/7/2021 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C. RESPONSE ON 12-7-21 FROM D.O.T. NEARING COMPLETION HOWEVER NOT COMPLETE YET.
12/20/2021 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C. RESPONSE ON 12-7-21 FROM D.O.T. NEARING COMPLETION HOWEVER NOT COMPLETE YET. AWAITING D.O.T. APPROVAL FOR PRIOR PHASE
2/7/2022 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C. RESPONSE ON 12-7-21 FROM D.O.T. NEARING COMPLETION HOWEVER NOT COMPLETE YET. AWAITING D.O.T. APPROVAL FOR PRIOR PHASE 2-7-22
3/4/2022 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C. RESPONSE ON 12-7-21 FROM D.O.T. NEARING COMPLETION HOWEVER NOT COMPLETE YET. AWAITING D.O.T. APPROVAL FOR PRIOR PHASE 2-7-22 STILL AWAITING D.O.T. APPROVAL ON PREVIOUS PHASE 3-4-22
3/22/2022 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C. RESPONSE ON 12-7-21 FROM D.O.T. NEARING COMPLETION HOWEVER NOT COMPLETE YET. AWAITING D.O.T. APPROVAL FOR PRIOR PHASE 2-7-22 STILL AWAITING D.O.T. APPROVAL ON PREVIOUS PHASE 3-4-22 SENT E-MAIL TO D.O.T. NO RESPONSE AWAITING APPROVAL OF TURN LANES TC 3-22-22
3/29/2022 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C. RESPONSE ON 12-7-21 FROM D.O.T. NEARING COMPLETION HOWEVER NOT COMPLETE YET. AWAITING D.O.T. APPROVAL FOR PRIOR PHASE 2-7-22 STILL AWAITING D.O.T. APPROVAL ON PREVIOUS PHASE 3-4-22 SENT E-MAIL TO D.O.T. NO RESPONSE AWAITING APPROVAL OF TURN LANES TC 3-22-22 NO RESPONSE FROM D.O.T. ON TURN LANE FINAL 3-29-22
3/29/2022 Plan Review - Documents Required NEED: NEED: CURRENT PERMIT 41533 FINALED OF FUEL SERVICE EXPANSION PRIOR TO BUILDING PERMIT FOR ADDITION, NEED: FDOT APPROVAL TO ISSUE THIS PERMIT- TC 11-5-21 CHECKING WITH D.O.T. FOR FINAL ON LAST PHASE 11-30-21 T.C. RESPONSE ON 12-7-21 FROM D.O.T. NEARING COMPLETION HOWEVER NOT COMPLETE YET. AWAITING D.O.T. APPROVAL FOR PRIOR PHASE 2-7-22 STILL AWAITING D.O.T. APPROVAL ON PREVIOUS PHASE 3-4-22 SENT E-MAIL TO D.O.T. NO RESPONSE AWAITING APPROVAL OF TURN LANES TC 3-22-22 NO RESPONSE FROM D.O.T. ON TURN LANE FINAL 3-29-22 DOT APPROVAL REC'D 3-29-22
3/30/2022 Plan Review - Plumbing Approved NEED:
3/30/2022 Plan Review - Mechanical Approved NEED:
3/30/2022 Plan Review - Electrical Approved NEED:
3/30/2022 Plan Review - Building Approved NEED:
3/30/2022 Final Review - Reviewed NEED:
3/30/2022 Final Review - Documents Required NEEDED: *MECHANICAL AND ROOFING SUB VF
3/31/2022 Final Review - Documents Required NEEDED: *MECHANICAL AND ROOFING SUB VF
4/4/2022 Final Review - Documents Required NEEDED: *MECHANICAL AND ROOFING SUB VF
4/25/2022 Final Review - Documents Required NEEDED: *MECHANICAL AND ROOFING SUB VF
5/19/2022 Final Review - Documents Required NEEDED: *MECHANICAL AND ROOFING SUB VF
5/26/2022 Final Review - Documents Required NEEDED: *MECHANICAL AND ROOFING SUB VF
6/3/2022 Final Review - Documents Required NEEDED: *MECHANICAL AND ROOFING SUB VF
6/16/2022 Final Review - Reviewed NEEDED: *MECHANICAL REGISTRATION
6/16/2022 Final Review - Payment Needed
6/17/2022 Permit Issued Permit #000044701 created and approved.
Contractors
Name/ Business License Title Role
Justin Phelps
Jm Phelps Construction
CBC1259784 Cert. Building Contractor
David P Wood
Wood's Electrical Services Inc
EC13002213 Electrical Contractor Subcontractor
Kevin Swinney
K & A Heating And Air Inc
County License & State License & Liability Insurance & Workers Comp Expired.
CAC1820676 Cert. A/c Class “b” Subcontractor
Scott Wolfe
Wolfe Plumbing Inc.
CFC051621 Plumbing Contractor Subcontractor
Joseph E Matthews
5-star Refrigeration + Ac Inc
County License & State License & Liability Insurance & Workers Comp Expired.
CMC046885 Cert. Mechanical Subcontractor
Inspections
Inspection Notes Performed By Date
Passed: Fire - Plan Review Lhill 12/13/2021
Rescheduled 7/20/2022:Electrical - Permanent Power Janice Williams 7/19/2022
Passed: Electrical - Permanent Power New Supply Location Troy Crews 7/20/2022
Release to power company Troy Crews 7/20/2022
Cancelled: Building - Slab Troy Crews 9/28/2022
Passed: Electrical - 1st Underground Rough–In Troy Crews 9/28/2022
Passed: Plumbing/Gas - 1st Underground Rough–In Troy Crews 9/28/2022
Passed: Building - Footer Troy Crews 10/6/2022
Passed: Engineering - Setbacks Troy Crews 10/6/2022
Passed: Building - Slab Troy Crews 10/6/2022
Passed: Building - Roof Decking Troy Crews 12/2/2022
Passed: Building - Framing Troy Crews 12/22/2022
Passed: Electrical - 2nd Rough-In Troy Crews 12/30/2022
Passed: Plumbing/Gas - 2nd Rough-In Troy Crews 12/30/2022
Passed: Building - Roof Decking Soffit Area Inside Store. Troy Crews 2/23/2023
Passed: Building - Lintel/Tie Beam Done In November 2022 After Slab Inspection. Troy Crews 2/23/2023
Cancelled: Building - Final Troy Crews 3/28/2023
Passed: Plumbing/Gas - Sanitary Final Troy Crews 3/28/2023
Passed: Plumbing/Gas - Water Pipe Final Troy Crews 3/28/2023
Rescheduled 4/19/2023:Building - Final Troy Crews 4/17/2023
Passed: Building - Final Put Gfci By Sink In Customer Area 3 Outlets, Fire Final Pending Troy Crews 4/19/2023
Passed: Fire - Fire Final Lance Hill 4/19/2023
Certificate-Release Certificate Fire Final And Outlets Installed By Sink Troy Crews 5/4/2023
Documents