Inspection |
Notes |
Performed By |
Date |
Rescheduled 7/25/2022:Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
7/22/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
Pictures Sent. |
Troy Crews |
7/25/2022 |
Passed: Building - Monolithic Slab |
|
Troy Crews |
7/30/2022 |
Passed: Engineering - Setbacks |
|
Troy Crews |
7/30/2022 |
Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
7/30/2022 |
Passed: Building - Masonry Wall Reinforcing |
|
Troy Crews |
8/10/2022 |
Passed: Electrical - Temporary Service |
|
Troy Crews |
8/10/2022 |
Release to power company |
|
Troy Crews |
8/10/2022 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
9/8/2022 |
Passed: Building - Framing |
Partial Roof Trusses |
Troy Crews |
9/8/2022 |
Cancelled: Building - Rated Assembly Fastening |
|
Troy Crews |
9/8/2022 |
Passed: Building - Roof Decking |
|
Troy Crews |
9/8/2022 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
9/22/2022 |
Passed: Mechanical - Rough In |
Partial |
Troy Crews |
9/22/2022 |
Rescheduled 9/23/2022:Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
9/22/2022 |
Rescheduled 9/26/2022:Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
9/23/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
Need City Gas Dept. To Check Pressure Test On All Gas Lines. |
Troy Crews |
9/26/2022 |
Passed: Building - Lath/Stucco |
|
Troy Crews |
10/12/2022 |
Cancelled: Electrical - Above Ceiling |
Duplicate |
Emaleigh Williams |
10/19/2022 |
Passed: Mechanical - Rough In |
|
Troy Crews |
10/20/2022 |
Passed: Electrical - Above Ceiling |
|
Troy Crews |
10/20/2022 |
Passed: Building - Final |
Partial Approval For Training And Cleaning Only. |
Troy Crews |
12/13/2022 |
Failed: Electrical - Permanent Power |
Not Complete, Labels, Knockout Covers Etc. Required. |
Troy Crews |
12/13/2022 |
Passed: Building - Final |
Release Of Co Pending Final City Approvals On Utility As Builts. |
Troy Crews |
12/16/2022 |
Passed: Electrical - Permanent Power |
Items Corrected. |
Troy Crews |
12/16/2022 |
Release to power company |
|
Troy Crews |
12/16/2022 |
Certificate-Release Certificate |
City Approvals Received |
Troy Crews |
12/28/2022 |
(Requested) Building-Monolithic Slab |
|
|
|
(Requested) Engineering-Setbacks |
|
|
|
(Requested) Electrical -1st Underground Rough–In |
|
|
|