4/12/2022
|
Application pending.
|
4/12/2022
|
Point Review - Processing
|
4/15/2022
|
Point Review - On Hold-Incomplete
PLEASE CONTACT ZONING @ 386-719-1474 FOR DETAILS-- MUST RECEIVE ZONING APPROVAL FOR NEW TOWERS
|
5/6/2022
|
Plan Review - Corrections Needed
NEEDED:
*CMC CONTRACTOR NOT ELIGIBLE TO PULL THIS TYPE OF PERMIT
*ELECTRICAL SUB VF
FOUNDATION PLANS AND TOWER PLANS MUST REFERENCE COMPLIANCE WITH THE 2020 FLORIDA BUILDING CODE
|
5/13/2022
|
Plan Review - Corrections Needed
NEEDED:
*CMC CONTRACTOR NOT ELIGIBLE TO PULL THIS TYPE OF PERMIT
*ELECTRICAL SUB VF
FOUNDATION PLANS AND TOWER PLANS MUST REFERENCE COMPLIANCE WITH THE 2020 FLORIDA BUILDING CODE
|
5/16/2022
|
Plan Review - Corrections Needed
NEEDED:
*CMC CONTRACTOR NOT ELIGIBLE TO PULL THIS TYPE OF PERMIT
*ELECTRICAL SUB VF
FOUNDATION PLANS AND TOWER PLANS MUST REFERENCE COMPLIANCE WITH THE 2020 FLORIDA BUILDING CODE
|
5/19/2022
|
Plan Review - Documents Required
NEEDED:
*CMC CONTRACTOR NOT ELIGIBLE TO PULL THIS TYPE OF PERMIT
*ELECTRICAL SUB VF
*FOUNDATION PLANS AND TOWER PLANS MUST REFERENCE COMPLIANCE WITH THE 2020 FLORIDA BUILDING CODE
|
5/23/2022
|
Plan Review - Documents Required
NEEDED:
*CMC CONTRACTOR NOT ELIGIBLE TO PULL THIS TYPE OF PERMIT
*ELECTRICAL SUB VF
*FOUNDATION PLANS AND TOWER PLANS MUST REFERENCE COMPLIANCE WITH THE 2020 FLORIDA BUILDING CODE
|
6/3/2022
|
Plan Review - Documents Required
NEEDED:
*CMC CONTRACTOR NOT ELIGIBLE TO PULL THIS TYPE OF PERMIT
*ELECTRICAL SUB VF
*FOUNDATION PLANS AND TOWER PLANS MUST REFERENCE COMPLIANCE WITH THE 2020 FLORIDA BUILDING CODE
|
6/6/2022
|
Plan Review - Documents Required
NEEDED:
*CMC CONTRACTOR NOT ELIGIBLE TO PULL THIS TYPE OF PERMIT
*ELECTRICAL SUB VF
*FOUNDATION PLANS AND TOWER PLANS MUST REFERENCE COMPLIANCE WITH THE 2020 FLORIDA BUILDING CODE
|
6/9/2022
|
Plan Review - Documents Required
NEEDED : PLANS MUST REFERENCE AND COMPLY WITH 2020 FLORIDA BUILDING CODE
|
6/13/2022
|
Plan Review - Documents Required
NEEDED : PLANS MUST REFERENCE AND COMPLY WITH 2020 FLORIDA BUILDING CODE
|
6/14/2022
|
Plan Review - Electrical Approved
|
6/14/2022
|
Plan Review - Building Approved
|
6/14/2022
|
Plan Review - Reviewed
|
6/14/2022
|
Zoning Review - Reviewed
|
6/14/2022
|
Final Review - Reviewed
|
6/14/2022
|
Point Review - Reviewed
|
6/14/2022
|
Permit Issued
Permit #000044680 created and approved.
|