Permit Details

Permit Search

Permit

Communications Tower

612 NE CLYDE VARNES RD
LAKE CITY, FL 32055

Permit #
000044680
Application #
54344
Status Completed
  1. Submitted Apr 12, 2022
  2. Issued Jun 14, 2022
  3. Expires Apr 10, 2023
  4. Completed Oct 12, 2022

Property

Parcel #
04927-000
Owner
Varnes Clyde F (ignite Wireless)
Acres
26.12
Subdivision
—
Zoning
A-2
Flood zone
A
District
1

Permit

Status
Completed
Septic release
N/A
Related permit
—

Job Details

Finished floor requirement
Fema map number
12023C0305D
This is the construction of a:
305ft Self Support Tower
Select access to property:
Culvert Permit
Total Estimated Cost
250000
Tower Height
305
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Is this a new or existing tower?
New
Service Amps
800

Status & Review History

  1. Application pending.
  2. Point Review - Processing
  3. Point Review - On Hold-Incomplete
  4. Plan Review - Corrections Needed
  5. Plan Review - Corrections Needed
  6. Plan Review - Corrections Needed
  7. Plan Review - Documents Required
  8. Plan Review - Documents Required
  9. Plan Review - Documents Required
  10. Plan Review - Documents Required
  11. Plan Review - Documents Required
  12. Plan Review - Documents Required
  13. Plan Review - Electrical Approved
  14. Plan Review - Building Approved
  15. Plan Review - Reviewed
  16. Zoning Review - Reviewed
  17. Final Review - Reviewed
  18. Point Review - Reviewed
  19. Permit Issued

Contractors

  • Kenneth Harbour

    Cleveland Mechanical

    License
    CGC1520767
    Title
    Cert. General
    Role
    Contractor

    County License & State License & Liability Insurance & Workers Comp Expired.

  • John Cleveland

    Cleveland Mechanical

    License
    EC0001621
    Title
    Cert. Electrical
    Role
    Subcontractor

    County License & State License & Liability Insurance & Workers Comp Expired.

Inspections

  1. Aug 11, 2022

    Passed: Building - Footer

    1 St Hole

    Inspected by Troy Crews

  2. Aug 11, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  3. Aug 16, 2022

    Passed: Building - Footer

    2 Nd Hole

    Inspected by Troy Crews

  4. Aug 16, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Aug 18, 2022

    Passed: Building - Footer

    3 Rd Hole

    Inspected by Troy Crews

  6. Aug 18, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  7. Sep 1, 2022

    Passed: Electrical - 1st Underground Rough–In

    Ground Ring And Conduits For Service

    Inspected by Troy Crews

  8. Sep 20, 2022

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  9. Sep 20, 2022

    Release to power company

    Inspected by Troy Crews

  10. Sep 21, 2022

    Release to power company

    Changed From Clay To Fpl

    Inspected by Melissa Garber

  11. Sep 26, 2022

    Passed: Building - Footer

    Looked At During Final Power

    Inspected by Troy Crews

  12. Sep 26, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  13. Sep 26, 2022

    Passed: Building - Slab

    Inspected by Troy Crews

  14. Oct 6, 2022

    Failed: Building - Final

    Now Power Meter Set And Slabs Not Poured.

    Inspected by Troy Crews

  15. Oct 12, 2022

    Passed: Building - Final

    Tower Job Only Generator And Co Location To Follow

    Inspected by Troy Crews