| Inspection |
Notes |
Performed By |
Date |
| Passed: Engineering - Initial Driveway |
|
Smith, Blake |
6/14/2022 |
| Passed: Building - Footer |
|
Troy Crews |
7/5/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
7/5/2022 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
7/7/2022 |
| Release to power company |
|
Troy Crews |
7/7/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Matt Forsyth |
7/28/2022 |
| Passed: Building - Slab |
|
Troy Crews |
8/3/2022 |
| Passed: Building - Slab |
|
Troy Crews |
8/3/2022 |
| Passed: Building - Roof Decking |
|
Troy Crews |
8/31/2022 |
| Passed: Building - Wall Sheathing |
|
Troy Crews |
8/31/2022 |
| Failed: Mechanical - Rough In |
No Seals On Registers, Bath Fan Not Installed Or Connected. |
Troy Crews |
9/16/2022 |
| Passed: Building - Framing |
|
Troy Crews |
9/16/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
10/28/2022 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
10/28/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Have Gas Provider Do Any Necessary Test And Final Connections.
|
Troy Crews |
10/28/2022 |
| Passed: Building - Insulation |
Must Have Access To Air Handler In Attic Prior To Final |
Troy Crews |
11/9/2022 |
| Septic Release Inspection |
|
Health Dept |
12/1/2022 |
| Passed: Electrical - Permanent Power |
Need Driveway Final |
Troy Crews |
2/8/2023 |
| Release to power company |
|
Melissa Garber |
2/10/2023 |
| Passed: Engineering - Final Driveway |
|
Smith, Blake |
2/10/2023 |
| Failed: Building - Final |
Unable To Access Attic Due To Stairs Being To Tight To Operate, Also Attic Stair Door Needs Fire Rating Same As Garage Ceiling, Need Defused In Front Small Room |
Gary Pitzer |
3/7/2023 |
| Passed: Building - Final |
|
Gary Pitzer |
3/9/2023 |