| Inspection |
Notes |
Performed By |
Date |
| Passed: Building - Footer |
|
Troy Crews |
7/12/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
7/12/2022 |
| Passed: Building - Framing |
Anchor Bolts Set In Epoxy Picture In File. |
Troy Crews |
8/17/2022 |
| Passed: Building - Framing |
Canopy Footers |
Troy Crews |
8/24/2022 |
| Passed: Building - Framing |
Closing In Ends Of Steel Beams Welded To Embeds |
Troy Crews |
8/31/2022 |
| Passed: Building - Framing |
Awning Framing |
Troy Crews |
9/14/2022 |
| Passed: Building - Slab |
Connector Slab From Addition To Garden Center |
Troy Crews |
9/21/2022 |
| Rescheduled 9/22/2022:Building - Framing |
|
Troy Crews |
9/22/2022 |
| Passed: Building - Framing |
Interior Columns Grouted |
Troy Crews |
9/22/2022 |
| Passed: Building - Roof Decking |
Roof Roof Deck Welded Curbs Also Welded Into Roof Deck |
Troy Crews |
9/22/2022 |
| Passed: Fire - Plan Review |
|
|
10/12/2022 |
| Passed: Mechanical - Rough In |
Freezer And Cooler Pickup 2 System Ducts. |
Anthony Aslan |
10/20/2022 |
| Cancelled: Fire - Sprinkler System Alteration |
|
Melissa Garber |
12/13/2022 |
| Cancelled: Fire - Fire Final |
|
Melissa Garber |
12/13/2022 |
| Cancelled: Fire - Sprinkler System Alteration |
|
Melissa Garber |
12/14/2022 |
| Cancelled: Fire - Fire Final |
|
Melissa Garber |
12/14/2022 |
| Passed: Fire - Fire Final |
|
Dwight Boozer |
12/14/2022 |
| Passed: Fire - Underground Main - Hydro |
|
Dwight Boozer |
12/14/2022 |
| Cancelled: Mechanical - Rough In |
|
Anthony Aslan |
12/19/2022 |
| Cancelled: Mechanical - Refrigeration |
|
Anthony Aslan |
12/19/2022 |
| Passed: Building - Final |
Release Of Completion Pending Fire Alarm Inspection By City Fire Dept. |
Troy Crews |
12/19/2022 |
| Cancelled: Mechanical - Rough In |
|
Troy Crews |
12/19/2022 |
| Cancelled: Mechanical - Refrigeration |
|
Troy Crews |
12/19/2022 |
| Passed: Building - Final |
Fire Alarm Inspection Done By Mr. Boozer |
Troy Crews |
2/2/2023 |
| (Requested) Fire-Fire Final |
|
|
|