Permit Details

Permit Search

Permit

Additions

12518 S US HIGHWAY 441
LAKE CITY, FL 32025

Permit #
000044544
Application #
54805
Status Completed
  1. Submitted May 12, 2022
  2. Issued May 26, 2022
  3. Expires Feb 7, 2024
  4. Completed Aug 11, 2023

Property

Parcel #
09419-102
Owner
The Cross Church Of
Acres
5.00
Subdivision
—
Zoning
A-3
Flood zone
X
District
4

Permit

Status
Completed
Septic release
Released
Related permit
—

Job Details

Elevation regulation
Site & Development Plan
Finished floor requirement
121.72'
Requirement needed
By Permanent Power Inspection
Document needed is
a Surveyor letter giving the Finished Floor Elevation
Document receieved
No
Fema map number
12023C0415C
Description of addition:
office space/storage/overflow
Select driveway access to property:
Existing Drive
Fire sprinklers?
No
Setbacks Front
30'
Setback Side 1
25'
Setback Side 2
25'
Setback Rear
25'
Stories
1
Heated Area (Sqft)
360
Total Area (Sqft)
2400
Total Estimated Cost
50000
Building Height
12
Building Code Construction Type
V
Building Code Element
B
Building Code Occupancy Types
Utility & Misc
Occupancy Use Title
church
Dev Permit #
F023-
Building Code Edition
2020 Florida Building Code 7th Edition and 2017 National Electrical Code
Septic#
22-0437
Is this an addition for commercial or residential use?
Commercial
Sealed roof decking options. (Must select one.)
Other (explain)
Sealed roof decking explanation for other option.
METAL BUILDING- SEE DRAWINGS FOR DETAILS
Service Amps
200

Status & Review History

  1. Point Review - Received-Hard Copy Application
  2. Plan Review - Documents Required
  3. Plan Review - Electrical Approved
  4. Plan Review - Building Approved
  5. Plan Review - Reviewed
  6. Zoning Review - Reviewed
  7. Final Review - Documents Required
  8. Final Review - Documents Required
  9. Final Review - Reviewed
  10. Final Review - Payment Needed
  11. Permit Issued
  12. Final Review - Payment Needed

Contractors

This is an owner-builder project.

Inspections

  1. May 24, 2022

    Passed: Fire - Plan Review

    Inspected by Lance Hill

  2. Jun 9, 2022

    Septic Release Inspection

    Inspected by Health Dept

  3. Sep 14, 2022

    Passed: Building - Monolithic Slab

    Inspected by Troy Crews

  4. Sep 14, 2022

    Passed: Engineering - Setbacks

    Inspected by Troy Crews

  5. Oct 4, 2022

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  6. Feb 17, 2023

    Passed: Electrical - 1st Underground Rough–In

    Inspected by Troy Crews

  7. Mar 21, 2023

    Passed: Electrical - Permanent Power

    Inspected by Troy Crews

  8. Mar 21, 2023

    Release to power company

    Inspected by Troy Crews

  9. Aug 10, 2023

    Rescheduled 8/11/2023:Building - Final

    Inspected by Troy Crews

  10. Aug 11, 2023

    Passed: Building - Final

    Inspected by Troy Crews