| 5/3/2022 |
Application pending. |
| 5/4/2022 |
Final Review - Contact the Building Dept |
| 5/5/2022 |
Point Review - Printed-Online Application |
| 5/5/2022 |
Point Review - Reviewed |
| 5/6/2022 |
Plan Review - Building Approved |
| 5/6/2022 |
Plan Review - Electrical Approved |
| 5/6/2022 |
Plan Review - Reviewed |
| 5/6/2022 |
Zoning Review - Reviewed |
| 5/6/2022 |
Final Review - Documents Required |
| 5/9/2022 |
Final Review - Documents Required |
| 5/13/2022 |
Final Review - Reviewed |
| 5/13/2022 |
Final Review - Reviewed |
| 5/13/2022 |
Final Review - Payment Needed |
| 5/19/2022 |
Final Review - Payment Needed |
| 5/23/2022 |
Final Review - Payment Needed |
| 5/23/2022 |
Permit Issued |