| Inspection |
Notes |
Performed By |
Date |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/20/2022 |
| Passed: Building - Footer |
|
Anthony Aslan |
5/20/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
7/12/2022 |
| Passed: Electrical - Temporary Service |
Ground Rod Needs To Be Drove In The Ground |
Anthony Aslan |
7/14/2022 |
| Release to power company |
|
Anthony Aslan |
7/14/2022 |
| Rescheduled 7/15/2022:Building - Slab |
|
Anthony Aslan |
7/14/2022 |
| Passed: Building - Slab |
|
Anthony Aslan |
7/15/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
10/3/2022 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
10/3/2022 |
| Failed: Building - Framing |
Plans On Site Are Not Plans Summitted To Bldg. Dept., Different Spacing For Rafters And Ceiling Joist. Windows Not Installed. Need Letter From Engineer For Rafters And Ceiling Joist. Plan Need To Be Summitted |
Anthony Aslan |
10/4/2022 |
| Cancelled: Building - Roof Decking |
|
Anthony Aslan |
11/1/2022 |
| Passed: Building - Framing |
|
Anthony Aslan |
11/1/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
8/23/2023 |
| Passed: Mechanical - Rough In |
Return Flex Loose At Plenum |
Anthony Aslan |
8/23/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Need To Relocate Tub Valve |
Anthony Aslan |
6/13/2024 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
6/20/2024 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Anthony Aslan |
6/20/2024 |
| Passed: Building - Insulation |
Walls And Ceiling Spray Foam |
Anthony Aslan |
7/1/2024 |
| Passed: Electrical - Permanent Power |
Need Septic Release |
Anthony Aslan |
7/24/2025 |
| Release to power company |
Rec'd Septic |
Ewilliams |
8/12/2025 |
| Septic Release Inspection |
|
Health Dept |
8/12/2025 |