| Passed: Building - Footer |
|
Troy Crews |
5/24/2022 |
| Passed: Engineering - Setbacks |
|
Troy Crews |
5/24/2022 |
| Passed: Electrical - Temporary Service |
|
Troy Crews |
5/24/2022 |
| Release to power company |
|
Troy Crews |
5/24/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
6/16/2022 |
| Passed: Building - Slab |
|
Troy Crews |
6/29/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
|
Anthony Aslan |
7/26/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
7/26/2022 |
| Cancelled: Building - Wall Sheathing |
|
Anthony Aslan |
7/26/2022 |
| Passed: Building - Framing |
D02 One Piece Engineering Missing, D07 Needs One More H2.5 @ Each End |
Anthony Aslan |
7/29/2022 |
| Passed: Electrical - 2nd Rough-In |
Reminder Chase Pipes For Circuits At Panel Not To Exceed 24 Inches In Length. |
Troy Crews |
8/12/2022 |
| Failed: Mechanical - Rough In |
Duct At Air Handler Location Not Complete. |
Troy Crews |
8/12/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
8/12/2022 |
| Passed: Building - Insulation |
|
Troy Crews |
8/22/2022 |
| Passed: Mechanical - Rough In |
|
Troy Crews |
8/22/2022 |
| Passed: Electrical - Permanent Power |
Need Septic Final And Driveway Final |
Troy Crews |
10/28/2022 |
| Release to power company |
Rec'd Final Drive And Septic |
Troy Crews |
11/8/2022 |
| Septic Release Inspection |
|
Health Dept |
11/9/2022 |
| Passed: Building - Final |
|
Troy Crews |
12/2/2022 |