| Passed: Engineering - Setbacks |
|
Anthony Aslan |
6/9/2022 |
| Passed: Building - Footer |
|
Anthony Aslan |
6/9/2022 |
| Passed: Electrical - 1st Underground Rough–In |
|
Troy Crews |
6/24/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Troy Crews |
6/24/2022 |
| Passed: Building - Slab |
|
Anthony Aslan |
6/27/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
7/29/2022 |
| Passed: Building - Framing |
Partial Framing, Waiting On Clarification From Engineer On Interior Bearing Walls. |
Anthony Aslan |
7/29/2022 |
| Passed: Electrical - 2nd Rough-In |
Need Nail Guards On Bearing Walls For Wires |
Anthony Aslan |
9/1/2022 |
| Passed: Mechanical - Rough In |
Need Insulation On Suction Line Coming Out Of Wall |
Anthony Aslan |
9/1/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
Nail Guard Living Room For Bath Room, Master Vent Marked On Outside Wall To Protect Vent |
Anthony Aslan |
9/1/2022 |
| Passed: Building - Insulation |
|
Anthony Aslan |
9/13/2022 |
| Septic Release Inspection |
|
Health Dept |
11/30/2022 |
| Passed: Electrical - Permanent Power |
|
Anthony Aslan |
12/20/2022 |
| Release to power company |
|
Anthony Aslan |
12/20/2022 |
| Failed: Building - Final |
Need Final Termite
a/c Condensers Not Anchored And Pads Need To Be Raised To Have 4" Exposed
island Outlets Not Tripping On Gfci |
Anthony Aslan |
1/30/2023 |
| Passed: Building - Final |
Need Final Termite |
Anthony Aslan |
2/1/2023 |
| Certificate-Release Certificate |
Recv'd Final Termite Spray |
Anthony Aslan |
2/3/2023 |