| Passed: Building - Footer |
|
Matt Forsyth |
8/9/2022 |
| Passed: Engineering - Setbacks |
|
Matt Forsyth |
8/9/2022 |
| Passed: Electrical - Temporary Service |
|
Matt Forsyth |
8/9/2022 |
| Release to power company |
|
Matt Forsyth |
8/9/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
9/19/2022 |
| Passed: Building - Slab |
Fibermesh Concrete |
Matt Forsyth |
10/12/2022 |
| Passed: Building - Roof Decking |
|
Matt Forsyth |
11/4/2022 |
| Passed: Building - Strapping |
|
Matt Forsyth |
11/4/2022 |
| Passed: Building - Wall Sheathing |
|
Matt Forsyth |
11/4/2022 |
| Passed: Building - Framing |
|
Matt Forsyth |
1/18/2023 |
| Passed: Electrical - 2nd Rough-In |
Light Switch At Top Of Stairs |
Matt Forsyth |
1/18/2023 |
| Passed: Mechanical - Rough In |
Check Clearance On Double Wall Pipe For Fireplace |
Matt Forsyth |
1/18/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
One Nail Plate Missing On Vent Stack |
Matt Forsyth |
1/18/2023 |
| Passed: Building - Insulation |
|
Troy Crews |
3/10/2023 |
| Septic Release Inspection |
|
Health Dept |
3/23/2023 |
| Passed: Electrical - Permanent Power |
|
Troy Crews |
5/17/2023 |
| Release to power company |
|
Troy Crews |
5/17/2023 |
| Passed: Building - Final |
Deadbolts Left |
Matt Forsyth |
7/28/2023 |