Inspection |
Notes |
Performed By |
Date |
Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/19/2022 |
Passed: Building - Footer |
Waiting On Picture Exiting Water Line In Footer |
Anthony Aslan |
5/19/2022 |
Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
6/17/2022 |
Cancelled: Building - Slab |
|
Anthony Aslan |
6/21/2022 |
Cancelled: Building - Slab |
|
Anthony Aslan |
6/21/2022 |
Cancelled: Building - Slab |
|
Anthony Aslan |
6/21/2022 |
Cancelled: Building - Slab |
|
Anthony Aslan |
6/21/2022 |
Cancelled: Building - Slab |
|
Anthony Aslan |
6/21/2022 |
Passed: Building - Slab |
|
Anthony Aslan |
6/24/2022 |
Passed: Building - Roof Decking |
|
Anthony Aslan |
11/9/2022 |
Passed: Building - Wall Sheathing |
Red Marks Missing Nails Told Framer |
Anthony Aslan |
11/9/2022 |
Passed: Electrical - 2nd Rough-In |
|
Troy Crews |
12/1/2022 |
Failed: Mechanical - Rough In |
Fresh Air Duct ?, Check All Kinked Ducts, One Bath Fan Not Ducted. |
Troy Crews |
12/1/2022 |
Passed: Plumbing/Gas - 2nd Rough-In |
|
Troy Crews |
12/1/2022 |
Failed: Building - Framing |
Check Strapping Truss Hg 8 B , Check Back Porch Lvl For More Nails Near Seams. |
Troy Crews |
12/1/2022 |
Passed: Building - Strapping |
|
Troy Crews |
12/1/2022 |
Passed: Building - Ext Strapping/Wall Sheathing |
|
Troy Crews |
12/1/2022 |
Passed: Building - Insulation |
Spray Foam |
Anthony Aslan |
12/27/2022 |
Passed: Building - Framing |
|
Anthony Aslan |
12/27/2022 |
Passed: Mechanical - Rough In |
Need Tape On Tore Flex Master Bedroom Side |
Anthony Aslan |
12/27/2022 |
Septic Release Inspection |
|
Health Dept |
3/8/2023 |
Failed: Electrical - Permanent Power |
Gate Would Not Open No One At Property. |
Troy Crews |
3/14/2023 |
Passed: Electrical - Permanent Power |
Private. Road |
Anthony Aslan |
3/15/2023 |
Release to power company |
|
Anthony Aslan |
3/15/2023 |
Passed: Building - Final |
|
Anthony Aslan |
5/4/2023 |