| Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/13/2022 |
| Passed: Building - Footer |
|
Anthony Aslan |
5/13/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
6/7/2022 |
| Passed: Building - Slab |
|
Anthony Aslan |
6/17/2022 |
| Failed: Building - Framing |
Spoke To Contractor |
Anthony Aslan |
10/27/2022 |
| Cancelled: Building - Framing |
|
Anthony Aslan |
11/8/2022 |
| Cancelled: Building - Framing |
|
Anthony Aslan |
11/8/2022 |
| Passed: Building - Roof Decking |
Inspected 10-27-22 |
Anthony Aslan |
11/16/2022 |
| Passed: Building - Ext Strapping/Wall Sheathing |
Inspected 10-27-22 |
Anthony Aslan |
11/16/2022 |
| Passed: Building - Framing |
|
Anthony Aslan |
11/16/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
4/13/2023 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
4/13/2023 |
| Passed: Plumbing/Gas - Tub Set/Shower Pan |
|
Anthony Aslan |
4/13/2023 |
| Failed: Mechanical - Rough In |
Master Exhaust Not Run Out Of Attic, Kitchen Exhaust Not Installed |
Anthony Aslan |
4/13/2023 |
| Passed: Mechanical - Rough In |
Kitchen Exhaust Installed |
Anthony Aslan |
5/8/2023 |
| Passed: Building - Insulation |
Spray Foam Attic |
Anthony Aslan |
5/8/2023 |
| Septic Release Inspection |
|
Health Dept |
7/14/2023 |
| Passed: Electrical - Permanent Power |
|
Anthony Aslan |
8/11/2023 |
| Release to power company |
|
Anthony Aslan |
8/11/2023 |
| Failed: Building - Final |
|
Anthony Aslan |
10/20/2023 |
| Passed: Building - Final |
|
Anthony Aslan |
10/23/2023 |