| Inspection |
Notes |
Performed By |
Date |
| Passed: Engineering - Setbacks |
|
Anthony Aslan |
5/3/2022 |
| Passed: Building - Footer |
Need Compaction Test (recv'd) |
Anthony Aslan |
5/3/2022 |
| Passed: Electrical - Temporary Service |
|
Anthony Aslan |
5/18/2022 |
| Release to power company |
|
Anthony Aslan |
5/18/2022 |
| Passed: Plumbing/Gas - 1st Underground Rough–In |
|
Anthony Aslan |
5/18/2022 |
| Passed: Building - Slab |
|
Anthony Aslan |
5/31/2022 |
| Passed: Electrical - 1st Underground Rough–In |
|
Anthony Aslan |
5/31/2022 |
| Cancelled: Building - Roof Decking |
|
Anthony Aslan |
6/29/2022 |
| Cancelled: Building - Wall Sheathing |
|
Anthony Aslan |
6/29/2022 |
| Cancelled: Building - Roof Decking |
|
Emaleigh Williams |
6/30/2022 |
| Cancelled: Building - Wall Sheathing |
|
Emaleigh Williams |
6/30/2022 |
| Passed: Building - Wall Sheathing |
|
Anthony Aslan |
6/30/2022 |
| Passed: Building - Roof Decking |
Just Garage Roof, Front Porch, Valleys To Garage |
Anthony Aslan |
6/30/2022 |
| Passed: Building - Roof Decking |
|
Anthony Aslan |
7/5/2022 |
| Passed: Electrical - 2nd Rough-In |
|
Anthony Aslan |
7/28/2022 |
| Passed: Plumbing/Gas - 2nd Rough-In |
|
Anthony Aslan |
7/28/2022 |
| Passed: Building - Framing |
Need Strap Back Porch Pocket Header In Master Bedroom |
Anthony Aslan |
7/28/2022 |
| Passed: Mechanical - Rough In |
|
Anthony Aslan |
8/8/2022 |
| Passed: Building - Insulation |
Walls, Knee Walls, Bonus Room |
Anthony Aslan |
8/16/2022 |
| Septic Release Inspection |
|
Health Dept |
9/13/2022 |
| Passed: Electrical - Permanent Power |
|
Anthony Aslan |
9/30/2022 |
| Release to power company |
|
Anthony Aslan |
9/30/2022 |
| Passed: Building - Final |
Master Bath Exterior Wall Outlet Open Ground Open Neutral
bonus Bath Open Ground Open Neutral
bonus Room Outlets Open Ground Open Neutral Afci |
Anthony Aslan |
1/9/2023 |